Acceptance of the Works Clause Samples

The 'Acceptance of the Works' clause defines the process by which the client formally acknowledges that the contractor has completed the agreed-upon work to the required standards. Typically, this involves an inspection or review period during which the client can identify any defects or incomplete items, after which the work is either accepted or a list of issues is provided for correction. This clause ensures that both parties have a clear, documented point at which responsibility for the work transfers and helps prevent disputes over whether the contractor’s obligations have been fulfilled.
POPULAR SAMPLE Copied 3 times
Acceptance of the Works. 23.1.1. When the Contractor believes that Practical Completion of the Works has been achieved it must notify the Principal‟s Representative or the Project Manager accordingly. 23.1.2. A joint inspection of the Works will be carried out by the Principal, the Principal‟s Representative and/or the Project Manager and the Contractor. 23.1.3. The Principal‟s Representative or the Project Manager will compile a list of defects and omissions (if any) and will furnish the Contractor with a copy together with written notice requiring the Contractor to rectify the same. 23.1.4. The Contractor must immediately execute and complete within a reasonable period all necessary rectification works. 23.1.5. On completion of the rectification works (other than minor defects or omissions permitted under the definition of Practical Completion in clause 1.1.1) to the satisfaction of the Principal‟s Representative or the Project Manager, the Principal‟s Representative or the Project Manager shall certify accordingly by issuing the Certificate of Practical Completion. 23.1.6. The Defects Liability Period shall begin from the date of the Certificate of Practical Completion issued by the Principal‟s Representative or the Project Manager. 23.1.7. During the Defects Liability Period the Principal‟s Representative or the Project Manager may notify the Contractor of any defects or omissions in the Works. 23.1.8. The Contractor must immediately execute and complete within a reasonable period all necessary rectification works. 23.1.9. In respect of defects and omissions in the Works required to be rectified by the Contractor under clause 23.1.8, the Defects Liability Period will be extended to a period of 12 months commencing on the completion of such rectification or further rectification, as the case may be. 23.1.10. The date of the Certificate of Practical Completion issued by the Principal‟s Representative or the Project Manager shall be the date of acceptance of the Works by the Principal, prior to which the Works shall not be considered as accepted, either in whole or in part. 23.1.11. The presence of the Principal, the Principal‟s Representative or the Project Manager during the execution of the Works, or use being made of part of the Works, shall not constitute acceptance of the Works or of part of the Works.
Acceptance of the Works. 5.1. The works performed by the Contractor during the contract shall be accepted in accordance to the annexed document “Statement of Work”.
Acceptance of the Works. Acceptance of the Works is subject to the provisions set forth in this Agreement and any applicable future Subdivision or Pre-Servicing Agreement
Acceptance of the Works. At the end of the warranty period, the Owner shall request, in writing, an inspection from the District Engineer and the District Engineer shall perform an inspection within 7 days of receipt of the request.
Acceptance of the Works. 8.1 Upon the completion of the Works, the Engineering Consultant shall, within fifteen (15) days, submit a Certificate of Completion (the “Certificate”) to the Director. The Director shall, within thirty (30) days of receipt of the Certificate, either advise the Engineering Consultant in writing that such Works have been satisfactorily completed, or set forth in writing particulars of any deficiencies regarding the Works. 8.2 The Owners agree that they shall rectify any deficiencies, as referred to in Section 8.1, within fifteen (15) days of receiving the written particulars of those deficiencies from the Director.
Acceptance of the Works. 15.1. When the CONTRACTOR considers the Works to be completed, it will notify the OWNER and the Architectural Supervision Team in writing to that effect, accompanying this notification with the following documentation corresponding to the works covered by this Contract: 1. Projects and Bulletins endorsed and legalised, and other certificates required by official bodies and utilities companies, corresponding to the installations covered by this Contract: electricity, telecommunications, heating, air conditioning, plumbing, sewerage, gas, fire protection, garage ventilation, lifts, exterior lighting, etc.
Acceptance of the Works. Maintenance and Repair of Public Works 5.9 Approval to Conduct Earthworks
Acceptance of the Works. The Acceptance of the Works by the Town shall be subject to the requirements of the Town’s Development Design Criteria and the Works will also be assessed against the drawings in Schedule “C” set out in this Agreement, all to the satisfaction of the Director of Development Services.
Acceptance of the Works. Acceptance of the Work shall occur at the Owners’ request subject to the certification of the Works by the Engineer and acceptance of same by the Director.

Related to Acceptance of the Works

  • Acceptance of the Work 19.1 No act of, or failure to act by, the Owner or the OWNER'S REPRESENTATIVE during the course of the Work, nor any extension of time for the completion of the Work, shall be regarded as an acceptance of such Work or any part thereof, or of materials used therein, either wholly or in part. Acceptance shall be evidenced only by the Final Payment by the Owner to Contractor. Before any final certificate shall issue, Contractor shall execute an affidavit on the certificate that it accepts the same in full payment and settlement of all claims on account of Work done and materials furnished under this Contract, and that all claims for materials provided or labor performed have been paid or set aside in full. No waiver of any breach of this Contract by the Owner or anyone acting on Owner's behalf shall be held as a waiver of any other subsequent breach thereof. 19.2 Contractor agrees to guarantee all work under this Contract for a period of one year from the date of Final Payment by the Owner or within such longer period of time as may be prescribed by law or by the terms of any applicable special guarantee required under terms of Owner’s conditional acceptance of elements of the Work the Owner deems marginally substandard. If any unsatisfactory condition or damage develops within the time of this guarantee period due to materials or workmanship that are defective, inferior, or not in accordance with the Contract, as reasonably determined by the Owner or the OWNER’S REPRESENTATIVE, then the Contractor shall, when notified by the Owner or OWNER’S REPRESENTATIVE, immediately place such guaranteed Work in a condition satisfactory to the Owner or OWNER’S REPRESENTATIVE. Such guarantee shall be in addition to any implied warranty under law or other manufacturer’s or product supplier’s warranty. The provisions of this Article apply to Work done by Subcontractors as well as to Work done by direct employees of the Contractor, and are in addition to any other remedies or warranties provided by law.

  • Acceptance of the Premises ‌ 3.1. “As Is” Condition of the Premises‌ The Lessee agrees to lease the Premises in their existing “as is” condition and acknowledges that in entering into this Lease, the Lessee does not rely on, and the Lessor does not make, any express or implied representations or warranties as to any matters, including any characteristics of the Premises or Improvements thereon, the suitability of the Premises for the intended use, the likelihood of deriving trade from or other characteristics of the Park Area, the economic or programmatic feasibility of the Lessee’s use and occupancy of the Premises, or Hazardous Materials on or in the vicinity of the Premises.

  • Acceptance of Work The completion of the Work shall be subject to acceptance by NYSERDA in writing of all deliverables as defined in Exhibit A, Statement of Work.

  • ACCEPTANCE OF EQUIPMENT The State will provide a written acknowledgment to the Contractor when the Equipment is accepted and performing satisfactorily.

  • Acceptance of Services Services furnished under this Contract are subject to acceptance by OSU. If OSU finds services furnished to be incomplete or not in compliance with the Contract, OSU, at its sole discretion, may either reject the services, require Contractor to correct any defects without charge, or negotiate with Contractor to reduce the price, whichever OSU deems appropriate under the circumstances. If Contractor is unable or refuses to cure any defects within a time deemed reasonable by OSU, OSU may reject the services and cancel the Contract in whole or in part.