Access Conditions. (a) Contractor shall have investigated and satisfied itself as to the suitability and availability of access routes to the Site and the Wairakei Station. (b) Where Contractor wishes to have other access or intrusion onto or over land adjoining either the Site or the Wairakei Station, then arrangements must be made by Contractor and such access or intrusion will be entirely at Contractor's risk and cost. Contractor shall keep Owner informed in respect of negotiations for any such arrangements and Owner's consent shall be required for any such arrangements (which consent shall not be unreasonably withheld).