Access to Project ROW Sample Clauses
The 'Access to Project ROW' clause defines the rights and procedures for parties to enter and use the project's right-of-way (ROW) areas. Typically, this clause outlines who may access the ROW, under what conditions, and for what purposes, such as construction, inspection, or maintenance activities. It may also specify requirements for advance notice, safety protocols, or limitations on access to protect ongoing work or property. The core function of this clause is to ensure orderly and authorized use of the project site, minimizing disruptions and clarifying responsibilities regarding site entry.
Access to Project ROW. To the extent that Developer has not been provided with access to portions of the Project ROW on or prior to the date set forth on the Project Schedule, Developer shall work around such Project ROW with the goals of minimizing delay to the completion of the Project. Except for delays caused by the type of event described in clause (b) of the definition of “TxDOT-Caused Delay” Developer shall not be entitled to any increase in the Price or time extension for delays caused by the failure or inability of TxDOT to provide Project ROW. Where Developer makes a request for access or rights of entry for any Project ROW for which access has not yet been acquired, Developer may, with TxDOT’s prior consent, which may be withheld or withdrawn at any time, in TxDOT’s discretion, and subject to the provisions of Section 3.12.8 above and Sections 7.3 and 7.4 of the Technical Provisions, negotiate with property owners or occupants for early access or temporary use of land, provided that any such negotiations shall comply in all respects with applicable Law, including the Uniform Act. Developer’s negotiations with property owners or occupants for early rights-of-entry shall occur only under such terms and conditions as are stipulated by TxDOT, in its discretion. TxDOT shall not be bound by the terms and conditions agreed upon by Developer and any property owner or occupant until such time as TxDOT has expressly so indicated in writing (and, then, only to the extent expressly set forth therein).
Access to Project ROW. To the extent that DB Contractor has not been provided with access to portions of the Project ROW on or prior to the date set forth on the Project Schedule, DB Contractor shall work around such Project ROW with the goals of minimizing delay to the completion of the Project. Except for delays caused by the type of event described in clause (b) of the definition of “TxDOT-Caused Delay” DB Contractor shall not be entitled to any increase in the Price or time extension for delays caused by the failure or inability of TxDOT to provide Project ROW.
Access to Project ROW. To the extent that Developer has not been provided with access to portions of the Project ROW on or prior to the date set forth on the Project Schedule, Developer shall work around such Project ROW with the goals of minimizing delay to the completion of the Project. Except for delays caused by the type of event described in clause (b) of the definition of “TxDOT-Caused Delay,” Developer shall not be entitled to any increase in the Price for delays caused by the failure or inability of TxDOT to provide Project ROW. Except for delays caused by the type of event described in Section 6.5.3, Developer shall not be entitled to any time extension for delays caused by the failure or inability of TxDOT to provide Project ROW. Where Developer makes a written request for access or rights of entry for any Project ROW for which access has not yet been acquired, Developer may, with TxDOT's prior written consent, which may be withheld or withdrawn at any time, in TxDOT’s sole discretion, and subject to the provisions of Section 6.6 above and Sections 7.4 and 7.5 of the Technical Provisions, negotiate with property owners or occupants for early access or temporary use of land, provided that any such negotiations shall comply in all respects with applicable Law, including the Uniform Act. Developer's negotiations with property owners or occupants for early rights-of-entry shall occur only under such terms and conditions as are stipulated by TxDOT, in its sole discretion. TxDOT shall not be bound by the terms and conditions agreed upon by Developer and any property owner or occupant until such time as TxDOT has expressly so indicated in writing (and, then, only to the extent expressly set forth therein).
Access to Project ROW. To the extent that Developer has not been provided with 20 access to portions of the Project ROW on or prior to the date set forth on the Project 21 Schedule, Developer shall work around such Project ROW with the goals of minimizing 22 delay to the completion of the Project. Except for delays caused by the types of events 23 described in clauses (d) and (e) of the definition of “ADOT-Caused Delay” Developer 24 shall not be entitled to any increase in the Price or Completion Deadline adjustment for 25 delays caused by the failure or inability of ADOT to provide Project ROW.
Access to Project ROW. To the extent that Developer has not been provided with access to portions of the Project ROW on or prior to the date set forth on the Project Schedule, Developer shall work around such Project ROW with the goals of minimizing delay to the completion of the Project. Except for delays caused by the type of event described in clause (b) of the definition of “TxDOT-Caused Delay” Developer shall not be entitled to any increase in the Price or time extension for delays caused by the failure or inability of TxDOT to provide Project ROW. Where Developer makes a written request for access or rights of entry for any Project ROW for which access has not yet been acquired, Developer may, with TxDOT's prior written consent, which may be withheld or withdrawn at any time, in TxDOT’s sole discretion, and subject to the provisions of Section 6.6 above and Sections
Access to Project ROW. 6.1.1 VPRA to Acquire Project ROW
Access to Project ROW. 34 5.9.2.1 To the extent that Developer has not been provided with 35 access to portions of the Project ROW on or prior to the date set forth on the Project 36 Schedule, Developer shall work around such Project ROW with the goals of minimizing 37 delay to the completion of the Project. Except for delays caused by the types of events 38 described in clauses (d) and (e) of the definition of “ADOT-Caused Delay” Developer 1 shall not be entitled to any increase in the Price or Completion Deadline adjustment for 2 delays caused by the failure or inability of ADOT to provide Project ROW. 7 Section 5.9.1 and Section DR 470.2.6 of the Technical Provisions, negotiate with 15 forth therein). All temporary entry agreements must be approved by FHWA.
Access to Project ROW. 5.9.2.1 To the extent that Developer has not been provided with
5.9.2.2 Where Developer makes a written request for access or
Access to Project ROW. To the extent that DB Contractor has not been provided with access to portions of the Project ROW on or prior to the date set forth on the Project Schedule, DB Contractor shall work around such Project ROW with the goals of minimizing delay to the completion of the Project. Except for delays caused by the type of event described in clause (b) of the definition of “TxDOT-Caused Delay” DB Contractor shall not be entitled to any increase in the Price or time extension for delays caused by the failure or inability of TxDOT to Texas Department of Transportation US 77 Upgrade from Kingsville to Driscoll Project October 3,23, 2012 30 RFP Addendum 12 Design-Build Agreement
Access to Project ROW. Formatted: No underline, Font color: Black