Common use of Action on Claims Clause in Contracts

Action on Claims. The Department’s failure to respond to a full and final documentation of Claim within 60 days shall constitute the Department’s rejection of the Claim. If the Department finds the Claim or any part thereof to be valid, the Department will (a) deliver to Developer written notice of determination authorizing such partial or whole Claim; (b) pay such Claim to the extent deemed valid (as to Extra Work Costs and Delay Costs, by one of the methods set forth in Section 9.3); and (c) grant a commensurate Completion Deadline adjustment, if applicable, as provided in the Contract Documents.

Appears in 2 contracts

Sources: Public Private Partnership Agreement, Public Private Partnership Agreement