Assumptions Utilized by Transmission Provider in Performing the System Impact Study. 1. Designated size: _ MW (wind or solar (CSP or PV), hydro, steam, or other type of energy) Generating Facility. 2. Generator type and number: ( Gen Mfgr Gen Model / Rating) turbines. 3. In addition to the study plan to identify Network Upgrades at the requested full output rating, also study the maximum generation level without Network Upgrades, up to the project size stated in the Interconnection Request: (Yes or No). (Note: Default assumption is “Yes”) 4. Intermediate project size also to be studied (refer to Section 3.4.4 of Transmission Provider’s GIP): MW. (Note: Default assumption is “None”) 5. Designated POI: (POI location description)