Authorization Required Prior to Parallel Operation. 2.2.1 The NYISO, in consultation with RG&E, shall use Reasonable Efforts to list applicable parallel Operating Requirements in Attachment 5 of this Agreement. Additionally, the NYISO shall notify RG&E of any changes to these requirements as soon as they are known. The NYISO shall make Reasonable Efforts to cooperate with RG&E in meeting requirements necessary to commence parallel operations by the in-service date. 2.2.2 RG&E shall not operate its Small Generating Facility in parallel with the New York State Transmission System or the Distribution System without prior written authorization of the NYISO. The NYISO will provide such authorization once the NYISO receives notification that RG&E has complied with all applicable parallel Operating Requirements. Such authorization shall not be unreasonably withheld, conditioned, or delayed.