Cost Responsibility for Interconnection Facilities Clause Samples

The 'Cost Responsibility for Interconnection Facilities' clause defines which party is financially responsible for the construction, installation, and maintenance of facilities needed to connect one party’s system to another’s, such as in utility or energy agreements. Typically, this clause specifies whether the interconnecting party, the utility, or both will bear the costs associated with new lines, substations, or upgrades required for the interconnection. By clearly allocating financial responsibility, the clause helps prevent disputes over payment and ensures that all parties understand their obligations regarding the expenses involved in establishing and maintaining the interconnection.
Cost Responsibility for Interconnection Facilities and Distribution Upgrades 8
Cost Responsibility for Interconnection Facilities and Distribution Upgrades 13 Article 5. Cost Responsibility for Network Upgrades 13 Article 6. Billing, Payment, Milestones, and Financial Security 15
Cost Responsibility for Interconnection Facilities and Distribution Upgrades 13 4.1 Interconnection Facilities 13 4.2 Distribution Upgrades 13 Article 5. Cost Responsibility for Network Upgrades 13 5.1 Applicability 13 5.2 Network Upgrades 13 5.2.1 Repayment of Amounts Advanced for Network Upgrades 14 5.3 Special Provisions for Affected Systems 15 5.4 Rights Under Other Agreements 15 Article 6. Billing, Payment, Milestones, and Financial Security 15 6.1 Billing and Payment Procedures and Final Accounting 15 6.2 Milestones 15 6.3 Advance Payment 16 Article 7. Assignment, Liability, Indemnity, Force Majeure, Consequential Damages, and Default 17 7.1 Assignment 17 7.2 Limitation of Liability 17 7.3 Indemnity 17 7.4 Consequential Damages 18 7.5 Force Majeure 18 7.6 Default 19 Article 8. Insurance 20 Article 9. Confidentiality 20 Article 10. Disputes 21 Article 11. Taxes 22
Cost Responsibility for Interconnection Facilities. 4.1 Each Interconnection Request submitted to the Public Utility must be accompanied by the required processing fee, pursuant to R746-312-6(4). The Interconnection Customer will bear the cost of any interconnection or other fees and charges provided for in the Rule. The Public Utility will not require any fees or charges for the Interconnection Customer to connect to the Public Utility’s Electric Distribution System or for operation and maintenance of a Generating Facility, except for the fees provided for in the Rule and this Interconnection Agreement, pursuant to R746-312-14(2). 4.2 The Interconnection Customer shall pay for the cost of the Interconnection Facilities itemized in Attachment 2 to this Interconnection Agreement. The Public Utility shall provide a best estimate cost, including overheads, for the purchase and construction of its Interconnection Facilities and provide a detailed itemization of such costs. Costs associated with Interconnection Facilities may be shared with other entities that may benefit from such facilities by agreement of the Interconnection Customer, such other entities, and the Public Utility. 4.3 The Interconnection Customer shall be responsible for its share of all reasonable expenses, including overheads, associated with owning, operating, maintaining, repairing, and replacing its own Interconnection Facilities.
Cost Responsibility for Interconnection Facilities. 4.1 The Interconnection Customer shall pay for the cost of the Interconnection Facilities itemized in Attachment 2 of this Agreement. The Transmission Owner shall provide the Parties a best estimate cost, including overheads, for the purchase and construction of the Transmission Owner Interconnection Facilities and provide a detailed itemization of such costs. Costs associated with Interconnection Facilities may be shared with other entities that may benefit from such facilities by agreement of the Interconnection Customer, such other entities, including the Transmission Owner and the Transmission Provider. 4.2 The Interconnection Customer shall be responsible for its share of all reasonable expenses, including overheads, associated with (1) owning, operating, maintaining, repairing, and replacing the Interconnection Customer’s Interconnection Facilities, and
Cost Responsibility for Interconnection Facilities and Distribution Upgrades 5 4.1 Interconnection Facilities 5 4.2 Distribution Upgrades 5 Article 5. Cost Responsibility for Network Upgrades 5 5.1 Applicability 5 5.2 Network Upgrades 5 2.1 Repayment of Amounts Advanced for Network Upgrades 6 5.3 Special Provisions for Affected Systems 7 5.4 Rights Under Other Agreements 7 Article 6. Billing, Payment, Milestones, and Financial Security 7 6.1 Billing and Payment Procedures and Final Accounting 7 6.2 Milestones 7 6.3 Advance Payment 8
Cost Responsibility for Interconnection Facilities and Distribution Upgrades (for distributed renewable generation greater than 100 kWAC and less than or equal to 2 MWAC) 11.01. The Customer shall pay JEA for the actual cost of any and all JEA Interconnection Facilities and Distribution Upgrades required to implement this Interconnection Agreement. JEA shall provide a best estimate cost, including overheads, for the purchase and construction of JEA’s Interconnection Facilities and Distribution Upgrades required and shall provide a detailed itemization of such costs. 11.02. The Customer shall be responsible for all reasonable expenses, including overheads, associated with: (a) owning, operating, maintaining, repairing, and replacing its own Interconnection Facilities and other equipment; and (b) operating, maintaining, repairing, and replacing JEA’s Interconnection Facilities and Distribution Upgrades. 11.03. JEA shall design, procure, construct, install and own the Interconnection Facilities and Distribution Upgrades, required for JEA to implement this Interconnection Agreement. If JEA and the Customer agree, the Customer may construct Interconnection Facilities and Distribution Upgrades that are located on land owned by the Customer. The actual cost of Interconnection Facilities and Distribution Upgrades, including overheads, shall be directly assigned to and paid by the Customer.
Cost Responsibility for Interconnection Facilities 

Related to Cost Responsibility for Interconnection Facilities

  • Cost Responsibility for Interconnection Facilities and Distribution Upgrades 4.1 Interconnection Facilities 4.2 Distribution Upgrades

  • Interconnection Customer’s Interconnection Facilities The Interconnection Customer shall design, procure, construct, install, own and/or control the Interconnection Customer’s Interconnection Facilities described in Appendix A at its sole expense.

  • Participating TO’s Interconnection Facilities The Participating TO shall design, procure, construct, install, own and/or control the Participating TO’s Interconnection Facilities described in Appendix A at the sole expense of the Interconnection Customer. Unless the Participating TO elects to fund the capital for the Participating TO’s Interconnection Facilities, they shall be solely funded by the Interconnection Customer.

  • Interconnection Facilities 4.1.1 The Interconnection Customer shall pay for the cost of the Interconnection Facilities itemized in Attachment 2 of this Agreement. The NYISO, in consultation with the Connecting Transmission Owner, shall provide a best estimate cost, including overheads, for the purchase and construction of its Interconnection Facilities and provide a detailed itemization of such costs. Costs associated with Interconnection Facilities may be shared with other entities that may benefit from such facilities by agreement of the Interconnection Customer, such other entities, the NYISO, and the Connecting Transmission Owner. 4.1.2 The Interconnection Customer shall be responsible for its share of all reasonable expenses, including overheads, associated with (1) owning, operating, maintaining, repairing, and replacing its own Interconnection Facilities, and

  • Purpose of Interconnection Facilities Except as may be required by Applicable Laws and Regulations, or as otherwise agreed to among the Parties, the Interconnection Facilities shall be constructed for the sole purpose of interconnecting the Large Generating Facility to the Participating TO’s Transmission System and shall be used for no other purpose.