Cost Responsibility for Interconnection Facilities and Distribution Upgrades Clause Samples

The 'Cost Responsibility for Interconnection Facilities and Distribution Upgrades' clause defines which party is financially responsible for the construction, modification, or upgrade of facilities needed to connect a new project—such as a power generator—to the existing utility grid. Typically, this clause specifies whether the project developer or the utility will pay for the necessary interconnection equipment and any required enhancements to the distribution system. For example, if a solar farm needs new transformers or upgraded lines to connect safely to the grid, this clause determines who bears those costs. Its core function is to allocate financial responsibility clearly, preventing disputes and ensuring that all parties understand their obligations regarding infrastructure investments.
POPULAR SAMPLE Copied 1 times
Cost Responsibility for Interconnection Facilities and Distribution Upgrades. 4.1 Interconnection Facilities 4.2 Distribution Upgrades
Cost Responsibility for Interconnection Facilities and Distribution Upgrades. 9.1. The Customer shall pay FPL for the actual cost of any and all FPL Interconnection Facilities and Distribution Upgrades, itemized in Attachment 2, required to implement this Interconnection Agreement. FPL shall provide a best estimate cost, including overheads, for the purchase and construction of FPL’s Interconnection Facilities and Distribution Upgrades required and shall provide a detailed itemization of such costs. 9.2. The Customer shall be responsible for all reasonable expenses, including overheads, associated with: i.) owning, operating, maintaining, repairing, and replacing its own Interconnection Facilities and other equipment; and ii.) operating, maintaining, repairing, and replacing FPL’s Interconnection Facilities and Distribution Upgrades. 9.3. FPL shall design, procure, construct, install and own the Interconnection Facilities and Distribution Upgrades, described in Attachment 2, required for FPL to implement this Interconnection Agreement. If FPL and the Customer agree, the Customer may construct Interconnection Facilities and Distribution Upgrades that are located on land owned by the Customer. The actual cost of Interconnection Facilities and Distribution Upgrades, including overheads, shall be directly assigned to and paid by the Customer.
Cost Responsibility for Interconnection Facilities and Distribution Upgrades. None The Interconnection Customer shall pay for the cost of the Interconnection Facilities itemized in Attachment 2 of this Agreement. The Transmission Owner shall provide a best estimate cost, including overheads, for the purchase and construction of its Interconnection Facilities and provide a detailed itemization of such costs. Costs associated with Interconnection Facilities may be shared with other entities that may benefit from such facilities by agreement of the Interconnection Customer, such other entities, and the Transmission Owner. The Interconnection Customer shall be responsible for its share of all reasonable expenses, including overheads, associated with (1) owning, operating, maintaining, repairing, and replacing its own Interconnection Facilities, and (2) operating, maintaining, repairing, and replacing the Transmission Owner’s Interconnection Facilities.
Cost Responsibility for Interconnection Facilities and Distribution Upgrades. 4.1 Interconnection Facilities 4.1. 1The Interconnection Customer shall pay for the cost of the Interconnection Facilities itemized in the Exhibits to this Agreement. If a Facilities Study was performed, T & D Utility shall identify its Interconnection Facilities necessary to safely interconnect the Small Generator Facility with T & D Utility's Electric Distribution System, the cost of those facilities, and the time required to build and install those facilities. 4.1. 2The Interconnection Customer shall be responsible for its share of all reasonable expenses, including overheads, associated with (1) owning, operating, maintaining, repairing, and replacing its Interconnection Equipment, and (2) operating, maintaining, repairing, and replacing T & D Utility’s Interconnection Facilities as set forth in the Exhibits to this Agreement.
Cost Responsibility for Interconnection Facilities and Distribution Upgrades. Interconnection Facilities The Interconnection Customer shall pay for the cost of the Interconnection Facilities itemized in the Exhibits to this Agreement. If a Facilities Study was performed, T & D Utility shall identify its Interconnection Facilities necessary to safely interconnect the Small Generator Facility with T & D Utility's Electric Distribution System, the cost of those facilities, and the time required to build and install those facilities. The Interconnection Customer shall be responsible for its share of all reasonable expenses, including overheads, associated with (1) owning, operating, maintaining, repairing, and replacing its Interconnection Equipment, and (2) operating, maintaining, repairing, and replacing T & D Utility’s Interconnection Facilities as set forth in the Exhibits to this Agreement. Distribution Upgrades T & D Utility shall design, procure, construct, install, and own any Distribution Upgrades. The actual cost of the Distribution Upgrades, including overheads, shall be directly assigned to the Interconnection Customer.
Cost Responsibility for Interconnection Facilities and Distribution Upgrades 

Related to Cost Responsibility for Interconnection Facilities and Distribution Upgrades

  • Network Upgrades and Distribution Upgrades The Participating TO shall design, procure, construct, install, and own the Network Upgrades and Distribution Upgrades described in Appendix A. The Interconnection Customer shall be responsible for all costs related to Distribution Upgrades. Unless the Participating TO elects to fund the capital for the Distribution Upgrades and Network Upgrades, they shall be solely funded by the Interconnection Customer.

  • Purpose of Interconnection Facilities Except as may be required by Applicable Laws and Regulations, or as otherwise agreed to among the Parties, the Interconnection Facilities shall be constructed for the sole purpose of interconnecting the Large Generating Facility to the Participating TO’s Transmission System and shall be used for no other purpose.

  • Contractor Responsibility for System Agency’s Termination Costs If the System Agency terminates the Contract for cause, the Contractor shall be responsible to the System Agency for all costs incurred by the System Agency and the State of Texas to replace the Contractor. These costs include, but are not limited to, the costs of procuring a substitute vendor and the cost of any claim or litigation attributable to Contractor’s failure to perform any Work in accordance with the terms of the Contract.