Common use of Baseline CPM Schedule Clause in Contracts

Baseline CPM Schedule. The Engineer and Contractor will review the draft baseline CPM schedule at a meeting specific for the review of the schedule. The Engineer will accept the draft baseline CPM schedule, provide review comments, or request additional information. Make appropriate adjustments or provide additional information within 14 calendar days. The Engineer’s acceptance is based solely on whether the baseline schedule meets the requirements of 108.03. Review comments made by the Engineer on the initial schedule will not relieve the Contractor from compliance with the Contract. The Contractor is responsible for scheduling, sequencing, and prosecuting the Work to comply with the Contract requirements.

Appears in 2 contracts

Sources: Construction Contract, Construction Contract