Billing and Payment of Overruns. If at any time during the performance of the Work prior to the initial True-Up Date, the Contract Sum exceeds the Target Price by more than [*], Contractor shall thereafter invoice Owner for only [*] of its Reimbursable Costs in its progress invoices delivered pursuant to Article 4.6. If there is an amount due from Contractor for an Overrun after the initial True-Up Date, Contractor shall pay such amount, adjusted to account for any reduced ▇▇▇▇▇▇▇▇ from Contractor pursuant to the first sentence of this Article 4.4.4, within twenty (20) calendar days after the True-Up Date. If the amount due from Contractor for an Overrun at the final True-Up Date is greater than the amount previously paid by Contractor with respect to the initial True-Up Date, Contractor shall pay such additional amount within twenty (20) calendar days after such True-Up Date.