Buyer’s Liability for Delay and Damage Sample Clauses

Buyer’s Liability for Delay and Damage. 5.6.1 Buyer shall pay Seller its actual costs, expenses or damages (including demurrage charges payable to third parties) incurred for each hour or part thereof that loading is delayed due to any of the reasons specified in (a) through (j) of Article 5.4. 5.6.2 Each vessel shall clear berth as soon as loading is completed and the delivery hoses are disconnected. Buyer shall pay Seller its actual costs, expenses or damages (including demurrage charges payable to third parties) incurred for each hour or part thereof in excess of two (2) hours that the vessel remains in berth subsequent to completion of loading and disconnection of the delivery hoses. Notwithstanding the foregoing, Buyer shall not be liable for the costs set forth above for all time in excess of four (4) hours after hoses have been disconnected, if (a) the reason for Buyer’s vessel not vacating the berth is Seller’s failure to deliver Cargo documents to Buyer’s vessel within such four (4) hour time period, or (b) such delay is the result of a Force Majeure event at the Loading Port or the berthing facilities. Notwithstanding the foregoing and the provisions of Article 12, if such delay is a result of the circumstances set forth in Article 5.4(l), then Buyer shall be liable for one-half of the expenses described above. 5.6.3 In the event that for any reason Buyer’s vessel causes damage to any facilities at the Loading Point and Seller is not timely compensated by the vessel causing the damage, then (a) Buyer shall reimburse Seller for the full cost of repair or replacement of such facilities without taking into account the depreciated value of such facilities; (b) any delay in loading the vessel as a result of such damage shall not be counted as used laytime or time on demurrage for such vessel, and (c) Buyer shall pay Seller its actual costs, expenses or damages (including demurrage charges to third parties) incurred for each hour or part thereof that any Loading Point may not be used as a result of such damage. Should any such damage occur, Buyer shall post such security for the payments provided in the preceding sentence as Seller may request; it being understood that Seller may detain the vessel at the Loading Port until such security shall have been posted.
Buyer’s Liability for Delay and Damage. 22.6.1 Buyer shall pay Seller at the rate of U.S.$1,000 per hour for each hour or part thereof that loading is delayed due to any of the reasons specified in clause (a), (b), (c), (d), (e) (but only to the extent that more than six hours are expended in discharging ballasts or slops) or (f) of Article 22.4. 22.6.2 Each tanker shall clear berth as soon as loading is completed and the delivery hoses are disconnected. Buyer shall pay Seller at the rate of U.S.$1,000 per hour for each hour or part thereof in excess of two hours that the tanker remains in berth subsequent to completion of loading and disconnection of the delivery hoses; provided, however, that such delay is caused by Buyer or the tanker. 22.6.3 In the event that for any reason Buyer's tanker causes damage to any facilities at the Loading Port, then (i) Buyer shall reimburse Seller for the cost of repair or replacement of such facilities, (ii) any delay in loading the tanker as a result of such damage shall not be counted as laytime for such tanker, and (iii) Buyer shall pay Seller at the rate U.S.$1,000 per hour for each hour or part thereof that any loading point may not be used as a result of such damage. Should any such damage occur, Buyer shall post such security for the payments provided in the preceding sentence as Seller may request, it being understood that Seller may detain the tanker at the Loading Port until such security shall have been posted.

Related to Buyer’s Liability for Delay and Damage

  • Liability for Damage Each party shall be liable to the other for all damage to the property of the other negligently, recklessly or intentionally caused by that party (or their agents, employees or invitees), except to the extent the loss is insured and subrogation is waived under the owner's policy.

  • Liability and Damages The liability provisions of the Terms shall apply except as explicitly agreed otherwise in this DPA.

  • Liability for Damages 1. The Purchaser shall be liable for any damages sustained by the State arising from Purchaser’s breach of the terms of this Contract and the State may cause all or part of the performance bond to be forfeited to recover such damages. 2. In the event that a portion of the timber sale under this Contract is resold as a result of the Purchaser’s forfeiture and the stumpage rate pursuant to the resold contract is lower than the stumpage rate provided herein, the difference between the original rate and the new rate shall be considered damages and the Purchaser shall be liable to the State for those damages. The State may cause all or part of the Purchaser’s performance bond to be forfeited to recover such damages.

  • NO LIMITATION OF LIABILITY FOR DAMAGES FOR PERSONAL INJURY OR PROPERTY DAMAGE ARE

  • No Damages for Delay The Contractor has no claim for monetary damages for delay or hindrances to the Work from any cause, including without limitation any act or omission of the Owner.