cannot be made. If Engineer is unable to certify payment in the amount of the Application, Engineer will notify Contractor and Owner as provided in Section 3.6.3.1. If Contractor and Engineer cannot agree on a revised amount, Engineer will promptly issue a Certificate for Payment for the amount for which Engineer is able to make these representations to Owner. Engineer shall also withhold the whole or part of a Certificate for Payment, or, because of subsequently discovered evidence, nullify the whole or a part of a Certificate for Payment previously issued, as necessary in Engineer’s opinion to protect Owner from loss for which Contractor is responsible, including loss resulting from acts and omissions of others for which Contractor is responsible under the Contract Documents, because of