Capacity of the Generating Facility. 6.10.1 If the Interconnection Request is for a Generating Facility that includes multiple energy production devices at a site for which the Interconnection Customer seeks a single Point of Interconnection, the Interconnection Request shall be evaluated on the basis of the aggregate capacity of the multiple devices, unless otherwise agreed to by the Utility and the Interconnection Customer. 6.10.2 For the purposes of this Standard, the capacity of the Generating Facility shall be considered the maximum rated capacity of the Generating Facility, except where the gross generating capacity of the Generating Facility is limited (e.g., through the use of a control system, power relay(s), or other similar device settings or adjustments as mutually agreed upon by the Utility and Interconnection customer). The Generating Facility’s capacity shall be considered the Maximum Generating Capacity specified by the Interconnection Customer in the Interconnection Request. The Maximum Generating Capacity approved in the Study Process will subsequently be included as a limitation in the Interconnection Agreement.
Appears in 4 contracts
Sources: Interconnection Procedures, Interconnection Procedures, Interconnection Procedures
Capacity of the Generating Facility. 6.10.1 6.10.1. If the Interconnection Request is for a Generating Facility that includes multiple energy production devices at a site for which the Interconnection Customer seeks a single Point of Interconnection, the Interconnection Request shall will be evaluated on the basis of the aggregate capacity of the multiple devices, unless otherwise agreed to by the Utility Cooperative and the Interconnection Customer.
6.10.2 6.10.2. For the purposes of this Standard, the capacity of the Generating Facility shall be considered the maximum rated capacity of the Generating Facility, except where the gross generating capacity of the Generating Facility is limited (e.g., through the use of a control system, power relay(s), or other similar device settings or adjustments as mutually agreed upon by the Utility Cooperative and Interconnection customerCustomer). The Generating Facility’s capacity shall be considered the Maximum Generating Capacity specified by the Interconnection Customer in the Interconnection Request. The Maximum Generating Capacity approved in the Study Process will subsequently be included as a limitation in the Interconnection Agreement.
Appears in 1 contract
Sources: Interconnection Procedures
Capacity of the Generating Facility. 6.10.1
6.10.1. If the Interconnection Request is for a Generating Facility that includes multiple energy production devices at a site for which the Interconnection Customer seeks a single Point of Interconnection, the Interconnection Request shall will be evaluated on the basis of the aggregate capacity of the multiple devices, unless otherwise agreed to by the Utility Cooperative and the Interconnection Customer.
6.10.2 6.10.2. For the purposes of this Standard, the capacity of the Generating Facility shall be considered the maximum rated capacity of the Generating Facility, except where the gross generating capacity of the Generating Facility is limited (e.g., through the use of a control system, power relay(s), or other similar device settings or adjustments as mutually agreed upon by the Utility Cooperative and Interconnection customerCustomer). The Generating Facility’s capacity shall be considered the Maximum Generating Capacity specified by the Interconnection Customer in the Interconnection Request. The Maximum Generating Capacity approved in the Study Process will subsequently be included as a limitation in the Interconnection Agreement.
Appears in 1 contract
Sources: Interconnection Procedures
Capacity of the Generating Facility. 6.10.1 If the Interconnection Request is for a Generating Facility that includes multiple energy production devices at a site for which the Interconnection Customer seeks a single Point of Interconnection, the Interconnection Request shall be evaluated on the basis of the aggregate capacity of the multiple devices, unless otherwise agreed to by the Utility and the Interconnection Customer.
6.10.2 For The Interconnection Request shall be evaluated using the purposes of this Standard, the capacity maximum ratedcapacity of the Generating Facility shall be considered the maximum rated capacity Nameplate Capacity of the Generating Facility, except where the gross generating capacity AC of the Generating Facility Facility, unless otherwise is limited (e.g., through the use of a control system, power relay(s), or other similar device settings or adjustments as mutually agreed upon toupon by the Utility and Interconnection customerCustomer). The Generating Facility’s capacity shall be considered the Maximum Generating Capacity specified by the Interconnection Customer Customer, in the Interconnection Request. The Maximum Generating Capacity approved in the Study Process will subsequently be included as a limitation in the Interconnection Agreement.
Appears in 1 contract
Sources: Generator Interconnection Procedures