Common use of Change Order Status Log Clause in Contracts

Change Order Status Log. On the last Working Day of each month, Design-Builder shall submit a log showing all Change Notices and their status. The log shall be organized by Change Notice number and for each Change Notice shall state, at a minimum: (a) a brief description of the issue; (b) an estimate of the anticipated cost; (c) an estimate of the schedule impact of the issue; (d) submission date of the Change Notice; (e) whether and when Design-Builder has submitted a Request for Change Order; (f) VPRA’s response to the Request for Change Order; (g) status of the Dispute Resolution Process; and (h) whether and when a Change Order has been issued. The log shall also show submitted requests to draw from the Allowance and provide the information listed in this Section 12.19 for each such request.

Appears in 2 contracts

Sources: Design Build Agreement, Design Build Agreement