Changes in the Quantities Clause Samples

POPULAR SAMPLE Copied 1 times
Changes in the Quantities. 38.1. If the final quantity of the work done differs from the quantity in the Bill of Quantities for the particular item by more than 25 percent provided the change is attributed to the Department i.e., either the B.O.Q. is prepared by the department or variation is due to change/ modification ordered by the Department and the same exceeds 1% of initial Contract Price, the Engineer shall adjust the rate to allow for the change, duly considering, (a) Justification for rate adjustment as furnished by the contractor, (b) Economies resulting from increase in quantities by way of reduced plant, equipment, and overhead costs, (c) Entitlement of contractor to compensation events where such events are caused by any additional work 38.2. The Engineer shall not adjust rates from changes in quantities if thereby the Initial Contract Price is exceeded by more than 15 per cent, except with the Prior approval of the Chief Engineer, PWD, ▇▇▇▇▇▇▇▇▇, Guwahati-3, Assam. 38.3. If requested by the Engineer, the Contractor shall provide the Engineer with a detailed cost break down of any rate in the Bill of Quantities.
Changes in the Quantities. 5.1 The contractor is bound to execute all supplemental works that are found essential, incidental and inevitable during execution of main work. 5.2 The rates of all such items shall be Estimated Rates plus or minus overall Tender premium.
Changes in the Quantities. 36.1. The Contractor is bound to carry out the items in the Bill of Quantities itemwise variation upto 25 per cent excess provided that the change does not exceeds 1% of initial Contract Price.
Changes in the Quantities. 41.1 If the final quantity of the work done differs from the quantity in the Bill of Quantities for the particular item by more than 25 percent, provided the change not exceeds 1 percent of the Initial Contract Price, the Project Manager shall adjust the rate to allow for the change.
Changes in the Quantities. 38.1.If the final quantity of the work done differs from the quantity in the Bill of Quantities for the particular item by more than 25 per cent provided the change exceeds 1 % of initial Contract Price, the Engineer shall adjust the rate to allow for the change, duly considering, (a) Justification for rate adjustment as furnished by the contractor, (b) Economies resulting from increase in quantities by way of reduced plant, equipment, and overhead costs, (c) Entitlement of the contractor to compensation events where such events are caused by any additional work 38.2. The Engineer shall not adjust rates from changes in quantities if thereby the Initial Contract Price is exceeded by more than 15 per cent, except with the Prior approval of the Employer. 38.3. If requested by the Engineer, the Contractor shall provide the Engineer with a detailed cost breakdown of any rate in the Bill of Quantities.
Changes in the Quantities. 38.1. If the final quantity of the work done differs from the quantity in the Bill of Quantities for the particular item by more than 25 percent provided the change is attributed to the Department i.e., either the B.O.Q. is prepared by the department or variation is due to change/ modification ordered by the Department and the same exceeds 1% of initial Contract Price, the Engineer shall adjust the rate to allow for the change, duly considering, (a) Justification for rate adjustment as furnished by the contractor, (b) Economies resulting from increase in quantities by way of reduced plant, equipment, and overhead costs, (c) Entitlement of contractor to compensation events where such events are caused by any additional work 38.2. The Engineer shall not adjust rates from changes in quantities if thereby the Initial Contract Price is exceeded by more than 15 per cent, except with the Prior approval of the Managing Director, ASDC for SC Ltd, Dispur, Guwahati-6 38.3. If requested by the Engineer, the Contractor shall provide the Engineer with a detailed cost break down of any rate in the Bill of Quantities.
Changes in the Quantities. 38.1 If the final quantity of the work done differs from the quantity in the ▇▇▇▇ of Quantities for the particular item by more than 25 percent provided the change exceeds 1% of Initial Contract Price, the Engineer shall adjust the rate to allow for the change. 38.2 The Engineer shall not adjust rates from changes in quantities if thereby the Initial Contract Price is exceeded by more than 15 percent, except with the Prior approval of the Employer. 38.3 If requested by the Engineer, the Contractor shall provide the Engineer with a detailed cost breakdown of any rate in the ▇▇▇▇ of Quantities.
Changes in the Quantities. 38.1. If the final quantity of the work done differs from the quantity in the Bill of Quantities for the particular item by more than 25 percent provided the change is attributed to the Department i.e., either the B.O.Q. is prepared by the department or variation is due to change/ modification ordered by the Department and the same exceeds 1% of initial Contract Price, the Engineer shall adjust the rate to allow for the change, duly considering, (a) Justification for rate adjustment as furnished by the contractor, (b) Economies resulting from increase in quantities by way of reduced plant, equipment, and overhead costs, (c) Entitlement of contractor to compensation events where such events are caused by any additional work

Related to Changes in the Quantities

  • Changes in the Work The Department may order changes in the work, the Contract Amount being adjusted accordingly. Any monetary adjustment or any substantive change in the work shall be in the form of an amendment, signed by both parties and approved by the State Purchases Review Committee. Said amendment must be effective prior to execution of the work.

  • MINOR CHANGES IN THE WORK If permitted in the agreement between Owner and Architect, the Architect has authority to order minor changes in the Work not involving adjustment in the Contract Sum or extension of the Contract Time and not inconsistent with the intent of the Contract Documents.

  • Changes to Specifications All Specifications and any changes thereto agreed to by the parties from time to time shall be in writing, dated and signed by the parties. Any change to the Process shall be deemed a Specification change. No change in the Specifications shall be implemented by Catalent, whether requested by Client or requested or required by any Regulatory Authority, until the parties have agreed in writing to such change, the implementation date of such change, and any increase or decrease in costs, expenses or fees associated with such change (including any change to Unit Pricing). Catalent shall respond promptly to any request made by Client for a change in the Specifications, and both parties shall use commercially reasonable, good faith efforts to agree to the terms of such change in a timely manner. As soon as possible after a request is made for any change in Specifications, Catalent shall notify Client of the costs associated with such change and shall provide such supporting documentation as Client may reasonably require. Client shall pay all costs associated with such agreed upon changes. If there is a conflict between the terms of this Agreement and the terms of the Specifications, this Agreement shall control. Catalent reserves the right to postpone effecting changes to the Specifications until such time as the parties agree to and execute the required written amendment.

  • Funding Restrictions and Order Quantities The Agency reserves the right to reduce or increase estimated or actual quantities in whatever amount necessary without prejudice or liability to the Agency, if: 12.3.1 Funding is not available; 12.3.2 Legal restrictions are placed upon the expenditure of monies for this category of service or supplies; or, 12.3.3 The Agency’s requirements in good faith change after award of the contract.

  • Changes in Equipment, Systems, Etc USBFS reserves the right to make changes from time to time, as it deems advisable, relating to its systems, programs, rules, operating schedules and equipment, so long as such changes do not adversely affect the services provided to the Trust under this Agreement.