CLAIMS FOR ADDITIONAL COST Clause Samples
POPULAR SAMPLE Copied 11 times
CLAIMS FOR ADDITIONAL COST. 12.3.1 If the Contractor wishes to make a claim for an increase in the Contract Sum, he shall give the Architect written notice thereof within twenty days after the occurrence of the event giving rise to such claim. This notice shall be given by the Contractor before proceeding to execute the Work, except in an emergency endangering life or property in which case the Contractor shall proceed in accordance with Paragraph 10.3 of these General Conditions. No such claim shall be valid unless so made. If the State and the Contractor cannot agree on the amount of the adjustment in the Contract Sum, it shall be determined by the Architect. Any change in the Contract Sum resulting from such claim shall be authorized by Change Order.
12.3.2 If the Contractor claims that additional cost is involved because of, but not limited to, (1) any order by the State to stop the Work pursuant to Paragraph 3.3 of these General Conditions where the Contractor was not at fault, or (2) failure of payment by the State pursuant to Paragraph 9.7(of these General Conditions), the Contractor shall make such claim as provided in Subparagraph 12.3.1 of this agreement.
12.3.3 The Architect will have authority to order minor changes in the Work not involving an adjustment in the Contract Sum or an extension of the Contract Time and not inconsistent with the intent of the Contract Documents. Such changes shall be effected by written order and shall be binding on the State and Contractor within 10 days unless the Contractor or the State objects to the change in writing.
CLAIMS FOR ADDITIONAL COST. If the Contractor wishes to make a Claim for an increase in the Contract Sum, written notice as provided herein shall be given before proceeding to execute the Work. Prior notice is not required for Claims relating to an emergency endangering life or property arising under Section 10.4.
CLAIMS FOR ADDITIONAL COST. 3.2.4, 3.3.1, 3.7.4, 7.3.9, 9.5.2, 10.2.5, 10.3.2, 15.1.5
CLAIMS FOR ADDITIONAL COST. If the Contractor wishes to make a Claim for an increase in the Contract Sum, written notice as provided in Section
CLAIMS FOR ADDITIONAL COST. 4.3.6.1 If the Contractor wishes to make Claim for an increase in the Contract Sum, written notice as provided herein shall be given before proceeding to execute the Work. Prior notice is not required for Claims relating to an emergency endangering life or property arising under Paragraph 10.3. If the Contractor believes additional cost is involved for reasons including but not limited to (1) a written interpretation from the Architect, (2) an order by the Owner to stop the Work where the Contractor was not at fault, (3) a written order for a minor change in the Work issued by the Architect, (4) failure of payment by the Owner, (5) termination of the contract by the Owner, (6) Owner's suspension or (7) other reasonable grounds. Claim shall be filed in accordance with the procedure established herein.
4.3.6.2 All claims as provided for in Paragraph 4.3.6 shall be made by specific written notice and shall detail all facts and issues substantiating the claim including all costs and expenses incurred or to be incurred.
CLAIMS FOR ADDITIONAL COST. 1.9.1. Contractor shall timely and officially certify all claims for additional cost and shall specifically comply with all provisions of the UGC to be considered valid. Note that only the Contractor can make a claim for additional cost under the terms of the Contract Documents.
CLAIMS FOR ADDITIONAL COST. If the Prime Contractor wishes to make a claim for an increase in the Contract Sum, written notice as provided in this Paragraph 4.3 shall be given before proceeding to execute the Work. Prior notice is not required for claims relating to an emergency endangering life or property arising under Paragraph 10.3. In addition, the Prime Contractor's request for an increase in the Contract Sum for any reason (other than work performed under emergency conditions) shall be made far enough in advance of required work to allow the Owner and the Architect/Engineer a sufficient amount of time, without adversely affecting the construction schedule, to review the request, prepare and distribute such additional documents as may be necessary to obtain suitable estimates or proposals and to negotiate, execute and distribute a Change Order for the required work if the Prime Contractor believes that additional cost is involved for reasons including but not limited to:
(1) a written interpretation from the Architect/Engineer;
(2) a written order for a minor change in the Work issued by the Architect/Engineer;
(3) failure of payment by the Owner;
(4) termination of the Contract by the Owner;
(5) the Owner’s temporary suspension of all or any portion of the Work where the Prime Contractor was not at fault; or
(6) other reasonable grounds.
CLAIMS FOR ADDITIONAL COST. 11.2.1 If the Contractor wishes to make a claim for an increase in the Contract Sum, he shall give the City written notice thereof within twenty (20) days after the occurrence of the event giving rise to such claim. This notice shall be given by the Contractor before proceeding to execute the Work. No such claim shall be valid unless so made. If the City and the Contractor cannot agree on the amount of the adjustment in the Contract Sum, it shall be determined by arbitration. Any change in the Contract Sum resulting from such claim shall be authorized by Change Order.
CLAIMS FOR ADDITIONAL COST. If the Contractor wishes to make Claim for an increase in the Contract Sum, written notice as provided herein shall be given before proceeding to execute the Work. Prior notice is not required for Claims relating to an emergency endangering life or property. If the Contractor believes additional cost is involved for reasons including but not limited to (1) a written interpretation from the ARCHITECT/ENGINEER, (2) an order by the Owner to stop the Work where the Contractor was not at fault, (3) a written order for a minor change in the Work issued by the ARCHITECT/ENGINEER, (4) failure of payment by the Owner, (5) termination of the Contract by the Owner, (6) Owner's suspension or (7) other reasonable grounds, Claim shall be filed in accordance with the procedure established herein.
CLAIMS FOR ADDITIONAL COST. No changes to the Work, the Contract Amount, the Project schedule(s) or other terms of the Subcontract are authorized unless approved in a written Change Order signed by an authorized JEG representative. No course of dealing or course of performance between the parties shall be the basis for an increase in the Contract Amount or an extension of the Project schedule(s). In the event that Subcontractor intends to Claim any increase in the Contract Amount as a result of any alleged change by JEG to the Work, Subcontractor shall give notice in writing to JEG within seven (7) days of the basis for the Claim, or as required by the JEG Contract, whichever is more stringent, of such change. Such notice from Subcontractor shall describe with reasonable detail the nature of such change and shall set forth in detail the alleged costs incurred by Subcontractor as a result of such change and the computation of the alleged increase to the Contract Amount that Subcontractor intends to Claim. Subcontractor's failure to provide timely notice of a Claim as required under this article is a full and complete waiver of its Claim. Pending a determination of the claimed adjustment, if any, Subcontractor shall proceed with its performance of the Work as changed. JEG shall not be obligated to pay Subcontractor a greater sum than JEG may recover under the JEG Contract for such increase to the Contract Amount claimed by Subcontractor resulting from such change. JEG shall have no further liability to Subcontractor of any type or amount with respect to such change.