Common use of Claims for Additional Time Clause in Contracts

Claims for Additional Time. If the Contractor wishes to make a Claim for an increase in the Contract Time, written notice as provided herein shall be given. The Contractor’s Claim shall include an estimate of cost and of probable effect of delay on progress of the Work. In the case of a continuing delay, only one Claim is necessary.

Appears in 14 contracts

Sources: Standard Form of Agreement Between Owner and Contractor for a Residential or Small Commercial Project, Standard Form of Agreement Between Owner and Contractor for a Residential or Small Commercial Project, Standard Form of Agreement Between Owner and Contractor for a Residential or Small Commercial Project

Claims for Additional Time. 1 If the Contractor wishes to make a Claim for an increase in the Contract Time, written notice as provided herein shall be given. The Contractor’s Claim shall include an estimate of cost and of probable effect of delay on progress of the Work. In the case of a continuing delay, only one Claim is necessary.

Appears in 14 contracts

Sources: Contract for Construction, Contract for Construction, Contract for Construction

Claims for Additional Time. If the Contractor wishes to make a Claim for an increase in the Contract Time, written notice as provided herein shall be given. The Contractor’s 's Claim shall include an estimate of the cost and of probable effect of delay on progress of the Work. In the case of a continuing delay, only one Claim is necessary.

Appears in 1 contract

Sources: Small Construction Projects Contract

Claims for Additional Time. a. If the Contractor wishes to make a Claim for an increase in the Contract Time, written notice notice, as provided herein required in this ARTICLE IV.2 shall be given. The Contractor’s Claim shall include an estimate of cost and of probable effect impact of delay on progress of the Work. In the case of a continuing delay, only one Claim is necessaryWork in accordance with ARTICLE III.

Appears in 1 contract

Sources: Professional Services Agreement

Claims for Additional Time. § 15.1.5.1 If the Contractor wishes to make a Claim for an increase in the Contract Time, written notice as provided herein shall be given. The Contractor’s Claim shall include an estimate of cost and of probable effect of delay on progress of the Work. In the case of a continuing delay, only one Claim is necessary.

Appears in 1 contract

Sources: Roof Replacement Agreement

Claims for Additional Time. If the Contractor wishes to make a Claim for an increase in the Contract Time, written notice as provided herein shall be given. The Contractor’s 's Claim shall include an estimate of cost and of probable effect of delay on progress of the Work. In the case of a continuing delay, only one Claim is necessary.

Appears in 1 contract

Sources: Request for Proposals

Claims for Additional Time. If the Contractor wishes to make a Claim for an increase in the Contract Time, written notice as provided herein shall be given. The Contractor’s 's Claim shall include an estimate of cost and of probable effect of delay on progress of the Work. In the case of a continuing delay, delay only one Claim is necessary.

Appears in 1 contract

Sources: Construction Contract

Claims for Additional Time. 4.2.7.1 If the Contractor wishes to make a Claim for an increase in the Contract Time, written notice as provided herein shall be given. The Contractor’s 's Claim shall include an estimate of cost and of probable effect of delay on progress of the Work. In the case of a continuing delay, delay only one Claim is necessary.

Appears in 1 contract

Sources: Construction Contract (National Instruments Corp /De/)