Common use of Claims for Additional Time Clause in Contracts

Claims for Additional Time. 4.3.7.1 If the Contractor wishes to make Claim for any increase in the Contract Time, specific written notice as defined in Paragraph 4.3.3 shall be given. The Contractor's Claim shall include an estimate of cost and of probable effect of delay on progress of the Work. In the case of a continuing delay only one Claim is necessary. 4.3.7.2 If adverse weather conditions are the basis for a Claim for additional time, such Claim shall be documented by data substantiating that weather conditions were abnormal for the period of time and could not have been reasonably anticipated, and that weather conditions had an adverse effect on the scheduled construction and that the conditions of 8.3.1.1 have been met as measured against the most recent Progress Schedule.

Appears in 16 contracts

Sources: Construction Management Agreement, Construction Management Agreement, Construction Management Agreement

Claims for Additional Time. 4.3.7.1 4.3.8.1 If the Contractor wishes to make Claim for any an increase in the Contract Time, specific written notice as defined in Paragraph 4.3.3 provided herein shall be given. The Contractor's Claim shall include an estimate of cost and of probable effect of delay on progress of the Work. In the case of a continuing delay only one Claim is necessary. 4.3.7.2 4.3.8.2 If adverse weather conditions are the basis for a Claim for additional time, such Claim shall be documented by data substantiating that weather conditions [were abnormal for the period of time and could not have been reasonably anticipated, and that weather conditions conditions] had an adverse effect on the scheduled construction and that the conditions of 8.3.1.1 have been met as measured against the most recent Progress Scheduleconstruction.

Appears in 1 contract

Sources: Construction Contract (Symantec Corp)

Claims for Additional Time. 4.3.7.1 4.3.8.1 If the Contractor wishes to make Claim for any an increase in the Contract Time, specific written notice as defined in Paragraph 4.3.3 provided herein shall be given. The Contractor's Claim shall include an estimate of cost and of probable effect of delay on progress of the Work. In the case of a continuing delay only one Claim is necessary. 4.3.7.2 4.3.8.2 If adverse weather conditions are the basis for a Claim for additional timetime in excess of that allowed for in the specification, such Claim shall be documented by data substantiating that weather conditions were abnormal for the period of time and could not have been reasonably anticipated, and that weather conditions had an adverse effect on the scheduled construction and that the conditions of 8.3.1.1 have been met as measured against the most recent Progress Scheduleconstruction.

Appears in 1 contract

Sources: Construction Contract (Monarch Casino & Resort Inc)