Common use of Claims for Additional Time Clause in Contracts

Claims for Additional Time. .1 If the Contractor wishes to make a Claim for an increase in the Contract Time, written notice as provided herein shall be given. The Contractor’s Claim shall include an estimate of cost and of probable effect of delay on progress of the Work. In the case of a continuing delay, only one Claim is necessary. .2 If adverse weather conditions are the basis for a Claim for additional time, such Claim shall be documented by data substantiating that weather conditions were abnormal for the period of time, could not have been reasonably anticipated and had an adverse effect on the scheduled construction.

Appears in 2 contracts

Sources: Contract for Construction, Contract for Construction

Claims for Additional Time. .1 If the Contractor wishes to make a Claim for an increase increases in the Contract Timetime to complete the Work, written notice as provided herein shall be given. The Contractor’s Claim shall include an estimate of cost and of probable probably effect of delay on progress of the Work. In the case of a continuing delay, only one Claim is necessary. .2 . If adverse weather conditions are the basis for a Claim for additional time, such Claim shall be documented by data substantiating that weather conditions were abnormal for the period of time, time and could not have been reasonably anticipated anticipated, and that weather conditions had an adverse effect on the scheduled construction.

Appears in 1 contract

Sources: Subcontract Agreement

Claims for Additional Time. .1 4.3.8.1 If the Contractor wishes to make a Claim for an increase in the Contract Time, written notice as provided herein shall be given. The Contractor’s 's Claim shall include an estimate of cost and of probable effect of delay on progress of the Work. In in the case of a continuing delay, delay only one Claim is necessary. .2 4.3.8.2 If adverse weather conditions are the basis for a Claim for additional time, such Claim shall be documented by data substantiating that weather conditions were abnormal for the period of time, time and could not have been reasonably anticipated anticipated, and that weather conditions had an adverse effect on the scheduled construction.

Appears in 1 contract

Sources: Construction Contract (Digex Inc/De)

Claims for Additional Time. .1 4.3.7.1 If the Contractor wishes to make a Claim for an increase in the Contract Time, written notice as provided herein shall be given. The Contractor’s Claim shall include an estimate of cost and of probable effect of delay on progress of the Work. In the case of a continuing delay, delay only one Claim is necessary. .2 4.3.7.2 If adverse weather conditions are the basis for a Claim for additional time, such Claim shall be documented by data substantiating that weather conditions were abnormal for the period of time, could not have been reasonably anticipated and had an adverse effect on the scheduled construction.

Appears in 1 contract

Sources: Construction Contract

Claims for Additional Time. .1 4.3.8.1 If the Contractor wishes to make a Claim for an increase in the Contract Time, written notice as provided herein shall be given. The Contractor’s 's Claim shall include an estimate of cost and of probable effect of delay on progress of the Work. In the case of a continuing delay, delay only one Claim is necessary. .2 4.3.8.2 If adverse weather conditions are the basis for a Claim for additional time, such Claim shall be documented by data substantiating that weather conditions were abnormal for the period of time, time and could not have been reasonably anticipated anticipated, and that weather conditions had an adverse effect on the scheduled construction.

Appears in 1 contract

Sources: Construction Contract (Digex Inc/De)

Claims for Additional Time. .1 If the Contractor wishes to make a Claim for an increase in the Contract TimeTime under a Work Order, written notice as provided herein shall be given. The Contractor’s Claim shall include an estimate of cost and of probable effect of delay on progress of the Work. In the case of a continuing delay, only one Claim is necessary. .2 . If adverse weather conditions are the basis for a Claim for additional time, such Claim shall be documented by data substantiating that weather conditions were abnormal for the period of time, could not have been reasonably anticipated and had an adverse effect on the scheduled construction.

Appears in 1 contract

Sources: Master Agreement for Civil Improvements

Claims for Additional Time. .1 If the Contractor wishes to make a Claim for an increase increases in the Contract Timetime to complete the Work, written notice as provided herein shall be given. The Contractor’s Claim shall include an estimate of cost and of probable effect of delay on progress of the Work. In the case of a continuing delay, only one Claim is necessary. .2 . If adverse weather conditions are the basis for a Claim for additional time, such Claim shall be documented by data substantiating that weather conditions were abnormal for the period of time, time and could not have been reasonably anticipated anticipated, and that weather conditions had an adverse effect on the scheduled construction.

Appears in 1 contract

Sources: Architectural Services Agreement

Claims for Additional Time. .1 § 15.1.5.1 If the Contractor wishes to make a Claim for an increase in the Contract Time, written notice as provided herein shall be given. The Contractor’s Claim shall include an estimate of cost and of probable effect of delay on d progress of the Work. In the case of a continuing delay, only one Claim is necessary. .2 § 15.1.5.2 If adverse weather conditions are the basis for a Claim for additional time, such Claim shall be documented by data substantiating that weather conditions were abnormal for the period of time, could not have been reasonably anticipated and had an adverse effect on the scheduled construction.

Appears in 1 contract

Sources: Construction Contract

Claims for Additional Time. .1 If the Contractor wishes to make a Claim for an increase in the Contract Time, written notice as provided herein shall be given. The Contractor’s Claim shall include an estimate of cost and of probable effect of delay on d progress of the Work. In the case of a continuing delay, only one Claim is necessary. .2 . § 17.9.5.2 If adverse weather conditions are the basis for a Claim for additional time, such Claim shall be documented by data substantiating that weather conditions were abnormal for the period of time, could not have been reasonably anticipated and had an adverse effect on the scheduled construction.

Appears in 1 contract

Sources: Standard Form of Agreement Between Owner and Contractor for a Residential or Small Commercial Project

Claims for Additional Time. .1 § 4.3.7.1 If the Contractor wishes to make a Claim for an increase in the applicable Contract Time, written notice as provided herein shall be given. The Contractor’s 's Claim shall include an estimate of cost and of probable effect of delay on progress of the Work. In the case of a continuing delay, delay only one Claim is necessary. .2 § 4.3.7.2 If adverse weather conditions are the basis for a Claim for additional time, such Claim shall be documented by data substantiating that weather conditions were abnormal for the period of time, could not have been reasonably anticipated and had an adverse effect on the scheduled construction.

Appears in 1 contract

Sources: Construction Contract (Sierra Pacific Resources /Nv/)

Claims for Additional Time. .1 15.1.5.1 If the Contractor wishes to make a Claim for an increase in the Contract Time, written notice as provided herein shall be given. The Contractor’s Claim shall include an estimate of cost and of probable effect of delay on progress of the Work. In the case of a continuing delay, only one Claim is necessary. .2 15.1.5.2 If adverse weather conditions are the basis for a Claim for additional time, such Claim shall be documented by data substantiating that weather conditions at the project site were abnormal for the period of time, could not have been reasonably anticipated and had an adverse effect on the scheduled construction.

Appears in 1 contract

Sources: Agreement Between Owner and General Contractor for Construction Services