Common use of COMPENSABLE DELAY Clause in Contracts

COMPENSABLE DELAY. For purposes of this Agreement, compensable delays (“Compensable Delay”) shall include only the following events and only if they impact the critical path of the Specific Project: (1) material neglectful act or omission by Exelon; and (2) material change ordered in the Work not due to Contractor’s fault.

Appears in 2 contracts

Sources: Consulting and Professional Services Agreement, Services Agreement

COMPENSABLE DELAY. For purposes of this Agreementthese Terms and Conditions, compensable delays (“Compensable Delay”) shall include only the following events and only if they impact the critical path of the Specific ProjectWork: (1) material neglectful act or omission by ExelonBuyer; and (2) material change ordered in the Work not due to Contractor’s fault.

Appears in 1 contract

Sources: Consulting and Professional Services Agreement