Completion of the Works. (a) Project Co shall complete the Works in accordance with this Project Agreement and achieve: (i) Substantial Completion by the Scheduled Substantial Completion Date; and (ii) Final Completion by the Scheduled Final Completion Date.

Appears in 8 contracts

Sources: Project Agreement, Project Agreement, Project Agreement

Completion of the Works. (a) Project Co shall complete the Works in accordance with this Project Agreement and achieve: (i) each Phase Completion by the applicable Scheduled Phase Completion Date; (ii) Tower Interim Completion by the Scheduled Tower Interim Completion Date; (iii) Substantial Completion by the Scheduled Substantial Completion Date; and (iiiv) Final Completion by the Scheduled Final Completion Date.

Appears in 3 contracts

Sources: Project Agreement, Project Agreement, Project Agreement

Completion of the Works. (a) Project Co shall complete the Works in accordance with this Project Agreement and achieve: (i) Interim Completion by the Scheduled Interim Completion Date; (ii) Substantial Completion by the Scheduled Substantial Completion Date; and (iiiii) Final Completion by the Scheduled Final Completion Date.

Appears in 1 contract

Sources: Project Agreement

Completion of the Works. (a) Project Co shall complete the Works in accordance with this Project Agreement and achieve: (i) each Interim Completion by the applicable Scheduled Interim Completion Date; (ii) Substantial Completion by the Scheduled Substantial Completion Date; and (iiiii) Final Completion by the Scheduled Final Completion Date.

Appears in 1 contract

Sources: Project Agreement

Completion of the Works. β€Œ (a) Project Co shall complete the Works in accordance with this Project Agreement and achieve: (i) Substantial Completion by the Scheduled Substantial Completion Date; and (ii) Final Completion by the Scheduled Final Completion Date.

Appears in 1 contract

Sources: Project Agreement

Completion of the Works. (a) Project Co shall complete the Works in accordance with this Project Agreement and achieve: (i) Phase Completion by the Scheduled Phase Completion Date; (ii) Substantial Completion by the Scheduled Substantial Completion Date; and (iiiii) Final Completion by the Scheduled Final Completion Date.

Appears in 1 contract

Sources: Project Agreement

Completion of the Works. (a) Project Co shall complete the Works in accordance with this Project Agreement and achieve: (i) Phase 1 Completion by the Scheduled Phase 1 Completion Date; (ii) Substantial Completion by the Scheduled Substantial Completion Date; and (iiiii) Final Completion by the Scheduled Final Completion Date.

Appears in 1 contract

Sources: Project Agreement

Completion of the Works. (a) Project Co shall complete the Works in accordance with this Project Agreement and achieve: (i) each Phase Completion by the applicable Scheduled Phase Completion Date; (ii) each Substantial Completion by the Scheduled Substantial Completion Date; and (iiiii) Final Completion by the Scheduled Final Completion Date.

Appears in 1 contract

Sources: Project Agreement