Concurrent Delays. To the extent the Design/Builder is entitled to an extension of time due to an Excusable Delay, but the performance of the Work would have been suspended, delayed or interrupted by the fault or neglect of the Design/Builder or by an Unexcusable Delay, the Design/Builder shall not be entitled to any additional costs for the period of such concurrency.
Appears in 10 contracts
Sources: Design/Build Agreement, Design/Build Agreement, Design/Build Agreement
Concurrent Delays. To the extent the Design/-Builder is entitled to an extension of time due to an Excusable Delay, but the performance of the Work would have been suspended, delayed or interrupted by the fault or neglect of the Design/-Builder or by an Unexcusable Delay, the Design/-Builder shall not be entitled to any additional costs for the period of such concurrency.
Appears in 1 contract
Sources: Design Build Agreement
Concurrent Delays. To the extent the Design/-Builder is entitled to an extension of time due to an Excusable Delayexcusable delay, but the performance of the Work would have been suspended, delayed delayed, or interrupted by the fault or neglect of the Design/-Builder or by an Unexcusable Delayinexcusable delay, the Design/-Builder shall not be entitled to any additional costs for cost during the period of such concurrency.
Appears in 1 contract
Sources: Design Build Agreement
Concurrent Delays. To the extent the Design/-Builder is entitled to an extension of time due to an Excusable Delayexcusable delay, but the performance of the critical path of the Work would have been otherwise suspended, delayed delayed, or interrupted by the fault or neglect of the Design/-Builder or by an Unexcusable Delayinexcusable delay, the Design/Design- Builder shall not be entitled to any additional costs for cost during the period of such concurrencyconcurrent delay.
Appears in 1 contract
Sources: Design Build Agreement
Concurrent Delays. To the extent the Design/-Builder is entitled to an extension of time due to an Excusable Delayexcusable delay, but the performance of the critical path of the Work would have been otherwise suspended, delayed delayed, or interrupted by the fault or neglect of the Design/-Builder or by an Unexcusable Delayunexcusable delay, the Design/Design- Builder shall not be entitled to any additional costs for cost during the period of such concurrencyconcurrent delay.
Appears in 1 contract
Sources: Design Build Agreement