Common use of Concurrent Delays Clause in Contracts

Concurrent Delays. To the extent the Construction Manager may be entitled to an extension of time due to an Excusable Delay, but the performance of the Work would have been suspended, delayed or interrupted by the fault or neglect of the Construction Manager or by an Inexcusable Delay, the Construction Manager shall not be entitled to any additional costs for the period of such concurrency.

Appears in 3 contracts

Sources: Construction Manager at Risk Agreement, Construction Manager at Risk Agreement, Construction Manager at Risk Agreement

Concurrent Delays. To the extent the Construction Manager may be entitled to an extension of time due to an Excusable Delay, but the performance of the Work would have been suspended, delayed delayed, or interrupted by the fault or neglect of the Construction Manager or by an Inexcusable Delay, the Construction Manager shall will not be entitled to any additional costs for the period of such concurrency.

Appears in 1 contract

Sources: Construction Manager at Risk Contract