Concurrent Delays. If there are concurrent delays and impacts, some of which entitle the Contractor to relief under this GC6.5 and some of which do not, the Contractor is not entitled to relief under this GC6.5, the Contractor shall be entitled to an extension of the Contract Time, and if applicable an adjustment of the Contract Price in respect of a Owner-Caused Event, only to the extent that the delays entitling the Contractor to relief under this GC6.5 exceed those that do not so entitle the Contractor to such relief; and
Appears in 3 contracts
Sources: Contracting Services Agreement, Form of Agreement, Consultant Agreement