Conditional Acceptance. Concrete may be accepted at the Engineer’s discretion with a warning that construction methods be examined to improve the durability criteria. A reduced payment shall be applied to all the relevant pay items under SABS 1200 G for the non-conforming element or concrete pour. Alternatively, the Contractor may elect to carry out remedial work to improve the durability of the concrete to the criterion of “Full Acceptance” to the satisfaction of the Engineer, and receive full payment. All proposed remedial measures shall be subject to the approval of the Engineer. The cost of all such remedial work shall be for the Contractor’s account.
Appears in 3 contracts
Sources: Construction Contract, Construction Contract, Construction Contract