Conduct of Test. Stability: For the one (1) hour prior to the start of and for the duration of the Performance Test, each Unit that is generating shall be operating in steady state mode with all Facility equipment in normal operating service. All non-generating units and plant equipment that affect auxiliary or station power usage shall be operating normally. The Facility, Unit or Units shall meet the stability requirements and stability thresholds established by the applicable ASME Performance Test Code, for the duration of each Test Period. If any stability measurement exceeds code requirements, then the Test Period will be deemed invalid unless otherwise agreed in writing by the parties.
Appears in 2 contracts
Sources: Tolling Power Purchase Agreement, Tolling Power Purchase Agreement