Confirmation of Scheduled Substantial Completion Date and Contract Price. 1.6.1 Contractor agrees that it has carefully evaluated the feasibility and practicality of performing the Work by the Scheduled Substantial Completion Date specified in the Contract Documents and for the Contract Price, without relying on any matter other than the Contract Documents, and confirms that such performance (including achievement of Substantial Completion by the Scheduled Substantial Completion Date, for the Contract Price) is feasible and practicable. 1.6.2 Contractor has, prior to the Effective Date, reviewed the Geotechnical Reference Reports and the Geotechnical Evaluation Report, inspected and examined the Site and surrounding locations and undertaken other appropriate activities sufficient to familiarize itself with surface conditions and subsurface conditions affecting the Work to the extent Contractor