Construction Means, Methods and Safety Clause Samples

The "Construction Means, Methods and Safety" clause defines the responsibility for determining and implementing the techniques, processes, and precautions necessary to complete construction work safely and effectively. Typically, this clause assigns the contractor the authority and obligation to select construction methods and ensure that all safety regulations and standards are followed on the job site. For example, the contractor must decide how to erect scaffolding or operate machinery while maintaining a safe environment for workers and the public. The core function of this clause is to clearly allocate responsibility for construction procedures and site safety, thereby reducing disputes and clarifying liability in the event of accidents or unsafe practices.
Construction Means, Methods and Safety. Consultant is not responsible for supervising, directing, controlling, or otherwise being in charge of the construction activities, means, methods or health or safety programs at the project site or in connection with the work; or supervising, directing, controlling, or otherwise being in charge of the actual work of the Construction Contractor, its sub-contractors, or other materialmen or service providers not engaged by Consultant.
Construction Means, Methods and Safety. It is understood that BDT has no control or authority over the means, methods, and sequences of construction; and therefore has no ongoing responsibility whatsoever for construction safety beyond its own personnel. Invoices for services and reimbursable expenses will be submitted monthly or at the completion of each phase of work and are due upon receipt. Invoices will be considered past due when unpaid after 30 days and subject to a service charge of 1.5 percent per month on the outstanding balance. In the event any portion of account remains unpaid 90 days after billing, Client shall pay cost of collection. BDT reserves the right to terminate performance of its services, without waiving any rights and without liability, for failure of Client to make payments in accordance with the provisions of this Agreement.
Construction Means, Methods and Safety. Unless the Architect has breached this Agreement or Architect or a Subconsultant has violated an Applicable Law, acted with willful misconduct or violated the standard of care set forth in Section 1.3, and then only to the extent of such breach, willful act or violation, Architect shall have no responsibility or liability with regard to, and Contractor and the Separate Contractors shall be solely responsible for, all selections (other than those selections expressly dictated by Architect or the Subconsultants in the Design Documents) of, and all supervision, implementation and enforcement relating to, construction means, methods, sequence, techniques, procedures or related matters involving health and safety of persons or protection of property at the Site during construction.
Construction Means, Methods and Safety. The CONSULTANT shall not have control over or charge of and shall not be responsible for construction means, methods, techniques, sequences or procedures, or for safety precautions and programs in connection with the construction, unless specifically identified in the Scope of Services.
Construction Means, Methods and Safety. The Engineer is not responsible for supervising, directing, controlling, or otherwise being in charge of the construction activities, means, or methods at the project site; or supervising, directing, controlling, or otherwise being in charge of the actual work of the Construction Contractor, its sub-contractors, or other materialmen or service providers not engaged by the Engineer. Party of the First Part ▇▇▇▇▇ ▇▇▇▇▇▇▇, City Attorney Kean Register, City Manager
Construction Means, Methods and Safety. It is understood that BDT has no control or authority over the means, methods, and sequences of construction; and therefore has no ongoing responsibility whatsoever for construction safety beyond its own personnel. Invoices for services and reimbursable expenses will be submitted monthly or at the completion of each phase of work and are due upon receipt. Invoices will be considered past due when unpaid after 30 days and subject to a service charge of 1.5 percent per month on the outstanding balance. In reserves the right to terminate performance of its services, without waiving any rights and without liability, for failure of Client to make payments in accordance with the provisions of this Agreement.

Related to Construction Means, Methods and Safety

  • Construction Methods 3.1 The Contractor shall provide all tools, equipment, materials, labor and work for the excavation and removal of the unsuitable subgrade soils and their subsequent replacement with the specified backfill soils as directed by the Owner’s representative. All work under this item shall be performed in a safe and workmanlike manner. 3.2 All work shall be performed in accordance with DelDOT Standard Specifications Section 821. 3.3 Following the removal of existing pavements, the Owner’s representative will review the exposed subgrade and provide recommendations for the undercutting of unsuitable subgrade materials as required. The depth and extent of undercut excavation, if required, will be determined by the Owner’s representative at the time of excavation. 3.4 All excavated materials shall become the property of the Contractor and be removed from the site at the completion of the project at no additional expense to the Owner. 3.5 Undercut excavations should be backfilled with graded aggregate. Backfill shall be placed in loose lifts not exceeding 8 inches thick. Each lift should be compacted with at least 3 passes of a minimum 5-ton, walk-behind or self-propelled vibratory roller when the size of the area permits, or with a vibrating plate mechanical compactor for smaller areas. Lift thickness shall be reduced to 6 inch loose lift when using a vibratory plate compactor. 3.6 The Contractor shall take precautions as necessary to minimize the potential for disturbance or softening of the pavement subgrade materials from inclement weather or construction traffic. As a minimum, this shall include the placement of backfill on the same day as the excavation. Any soft areas which develop shall be undercut and replaced with graded aggregate at no additional cost to the Owner. 3.7 Where undercutting is performed, the geotextile fabric shall be installed. The fabric should be pulled tight and lapped a minimum of 12 inches.

  • CONTRACT WORK HOURS AND SAFETY STANDARDS As per the Contract Work Hours and Safety Standards Act (40 U.S.C. 3701-3708), where applicable, all Customer Purchase Orders in excess of ,000 that involve the employment of mechanics or laborers must include a provision for compliance with 40 U.S.C. 3702 and 3704, as supplemented by Department of Labor regulations (29 CFR Part 5). Under 40 U.S.C. 3702 of the Act, each contractor must be required to compute the wages of every mechanic and laborer on the basis of a standard work week of 40 hours. Work in excess of the standard work week is permissible provided that the worker is compensated at a rate of not less than one and a half times the basic rate of pay for all hours worked in excess of 40 hours in the work week. The requirements of 40 U.S.C. 3704 are applicable to construction work and provide that no laborer or mechanic must be required to work in surroundings or under working conditions which are unsanitary, hazardous or dangerous. These requirements do not apply to the purchases of supplies or materials or articles ordinarily available on the open market, or contracts for transportation or transmission of intelligence.

  • Other Methods of Procurement of Goods and Works The following table specifies the methods of procurement, other than International Competitive Bidding, which may be used for goods and works. The Procurement Plan shall specify the circumstances under which such methods may be used: (a) National Competitive Bidding (b) Shopping (c) Direct Contracting

  • Interconnection Facilities Engineering Procurement and Construction Interconnection Facilities, Network Upgrades, and Distribution Upgrades shall be studied, designed, and constructed pursuant to Good Utility Practice. Such studies, design and construction shall be based on the assumed accuracy and completeness of all technical information received by the Participating TO and the CAISO from the Interconnection Customer associated with interconnecting the Large Generating Facility.

  • Construction, Etc Each covenant contained herein shall be construed (absent express provision to the contrary) as being independent of each other covenant contained herein, so that compliance with any one covenant shall not (absent such an express contrary provision) be deemed to excuse compliance with any other covenant. Where any provision herein refers to action to be taken by any Person, or which such Person is prohibited from taking, such provision shall be applicable whether such action is taken directly or indirectly by such Person. For the avoidance of doubt, all Schedules and Exhibits attached to this Agreement shall be deemed to be a part hereof.