Construction Methodology for Cross Bay Link Sample Clauses

Construction Methodology for Cross Bay Link. 4.2.1 The major construction works would comprise the following activities: 4.2.2 No dredging works are envisaged for the construction of CBL. 4.2.3 Piling and pile cap construction would occur in three different sections for the Main Bridge, Eastern Approach and Western Approach. 4.2.4 Marine drilling rigs would be used for the installation of piles. One drilling rig to be used for the Eastern Approach foundations and one drilling rig to be used for the Western Approach as well as the Main Bridge foundations. There would be two marine piling fronts in total and the works undertaken in the following sequence. 4.2.5 A silt curtain would be placed around each foundation construction location to form the first line of defence against dispersion of sediment plume during pile, pile cap and pier construction. Steel sheet piling would be undertaken within the silt curtain to form a cofferdam and a second line of defence against dispersion of sediment plume during excavation of piles and construction of the pile cap. 4.2.6 Cylindrical steel casings (of the pile diameter) would be installed at each pile location within the steel sheet pile cofferdam. Excavation from within the cylindrical steel casing would be undertaken from the seabed level down to the pile founding level. The excavated materials would be transported from cylindrical steel casing by watertight closed-grab to a construction barge. 4.2.7 Following the excavation stage, a steel reinforcement cage would be lowered to the excavated void within the cylindrical steel casing. Concrete would then be poured by skipper to fill up the excavated void. The cylindrical steel casing would then be slowly retrieved by vertical pull during the concreting work. 4.2.8 For construction of the pile cap, temporary false work and formwork would be erected within the steel sheet pile cofferdam, the reinforcement placed into position and concrete would be placed to complete the pile cap. 4.2.9 This construction method would avoid the need to dredge sediment because the pile cap would be located above the sea bed. Sediment excavated from within the cylindrical steel pile casings would be placed in a barge and disposed in accordance with regulations. 4.2.10 ▇▇▇▇▇▇▇ ▇▇▇▇▇▇ would be used to transport steel pile casings to foundation locations and a crane would lift and place them into position. The pile casing would be installed using a hammer rig and the concrete would be supplied by another barge containing the concrete lorr...

Related to Construction Methodology for Cross Bay Link

  • Construction Methods 3.1 The Contractor shall provide all tools, equipment, materials, labor and work for the excavation and removal of the unsuitable subgrade soils and their subsequent replacement with the specified backfill soils as directed by the Owner’s representative. All work under this item shall be performed in a safe and workmanlike manner. 3.2 All work shall be performed in accordance with DelDOT Standard Specifications Section 821. 3.3 Following the removal of existing pavements, the Owner’s representative will review the exposed subgrade and provide recommendations for the undercutting of unsuitable subgrade materials as required. The depth and extent of undercut excavation, if required, will be determined by the Owner’s representative at the time of excavation. 3.4 All excavated materials shall become the property of the Contractor and be removed from the site at the completion of the project at no additional expense to the Owner. 3.5 Undercut excavations should be backfilled with graded aggregate. Backfill shall be placed in loose lifts not exceeding 8 inches thick. Each lift should be compacted with at least 3 passes of a minimum 5-ton, walk-behind or self-propelled vibratory roller when the size of the area permits, or with a vibrating plate mechanical compactor for smaller areas. Lift thickness shall be reduced to 6 inch loose lift when using a vibratory plate compactor. 3.6 The Contractor shall take precautions as necessary to minimize the potential for disturbance or softening of the pavement subgrade materials from inclement weather or construction traffic. As a minimum, this shall include the placement of backfill on the same day as the excavation. Any soft areas which develop shall be undercut and replaced with graded aggregate at no additional cost to the Owner. 3.7 Where undercutting is performed, the geotextile fabric shall be installed. The fabric should be pulled tight and lapped a minimum of 12 inches.

  • Construction Progress Schedule A schedule indicating proposed activity sequences and durations, milestone dates for receipt and approval of pertinent information, preparation, submittal, and processing of Shop Drawings and Samples, delivery of materials or equipment requiring long-lead time procurement, and proposed date(s) of Material Completion and Occupancy and Final Completion. The schedule will be developed to represent the sixteen or seventeen CSI Specification Divisions. It shall have a minimum number of activities as required to adequately represent to Owner the complete scope of work and define the Project’s critical path and associated activities. If the Project is to be phased, then each individual Phase should be identified from start through completion of the overall Project and should be individually scheduled and described, including any Owner’s occupancy requirements and showing portions of the Project having occupancy priority. The format of the schedule will have dependencies indicated on a monthly grid identifying milestone dates such as construction start, phase construction, structural top out, dry-in, rough-in completion, metal stud and drywall completion, equipment installation, systems operational, Material Completion and Occupancy Date, final inspection dates, Punchlist, and Final Completion date.

  • Information Systems Acquisition Development and Maintenance a. Client Data – Client Data will only be used by State Street for the purposes specified in this Agreement.

  • Network Interconnection Methods 3.1 The Interconnection provided herein may not be used solely for the purpose of originating a Party’s own interexchange traffic.

  • Attachment A, Scope of Services The scope of services is amended as follows: