Construction Scheduling Support Services Primavera Scheduling Software. a. Contract Time Determination • The Engineer shall develop a contract time determination schedule for the State’s use in establishing the working days for the PS&E. • The Engineer shall use production rates approved by the State. • The Engineer shall use Primavera scheduling software unless directed otherwise by the State. • The Engineer shall use appropriate calendars and coding for modeling the type of work and incorporate weather and other constraints in the calendars. • The contract time calendar should conform to the definition of a working day as defined in the PS&E. • The Engineer shall develop the time determination schedule to follow the traffic control plans taking into consideration the breakdown of quantities of work to be done in each phase. • The Engineer shall review contract time determination schedules and provide a written summary of findings.
Appears in 3 contracts
Sources: Contract for Engineering Services, Contract for Engineering Services, Contract for Engineering Services