Contents of Time Extension Requests. The Contractor shall provide with each time extension request a quantitative demonstration of the impact of the delay on project completion time, based on the Work Progress Schedule. The Contractor shall include with Time Extension Requests a reasonably detailed narrative setting forth: 9.9.3.1 The nature of the delay and its cause; the basis of the Contractor’s claim of entitlement to a time extension. 9.9.3.2 Documentation of the actual impacts of the claimed delay on the critical path indicated in the Contractor’s Work Progress Schedule, and any concurrent delays. 9.9.3.3 Description and documentation of steps taken by the Contractor to mitigate the effect of the claimed delay, including, when appropriate, the modification of the Work Progress Schedule.
Appears in 41 contracts
Sources: Construction Management Agreement, Construction Management Agreement, Design Build Contract
Contents of Time Extension Requests. The Contractor shall provide with each time extension request Time Extension Request a quantitative demonstration of the impact of the delay on project completion time, based on the Work Progress Schedule. The Contractor shall include with Time Extension Requests a reasonably detailed narrative setting forth:
9.9.3.1 The nature of the delay and its cause; the basis of the Contractor’s claim of entitlement to a time extension.
9.9.3.2 Documentation of the actual impacts of the claimed delay on the critical path indicated in the Contractor’s Work Progress Schedule, and any concurrent delays.
9.9.3.3 Description and documentation of steps taken by the Contractor to mitigate the effect of the claimed delay, including, when appropriate, the modification of the Work Progress Schedule.
Appears in 34 contracts
Sources: General Construction Services Contract, Construction Services Agreement, Job Order
Contents of Time Extension Requests. The Contractor shall provide with each time extension request a quantitative demonstration of the impact of the delay on project Project completion time, based on the Work Progress Schedule. The Contractor shall include with Time Extension Requests a reasonably detailed narrative setting forth:
9.9.3.1 The nature of the delay and its cause; the basis of the Contractor’s claim of entitlement to a time extension.
9.9.3.2 Documentation of the actual impacts of the claimed delay on the critical path indicated in the Contractor’s Work Progress Schedule, and any concurrent delays.
9.9.3.3 Description and documentation of steps taken by the Contractor to mitigate the effect of the claimed delay, including, when appropriate, the modification of the Work Progress Schedule.
Appears in 17 contracts
Sources: Construction Management Agreement, Construction Management Agreement, Owner and Contractor Agreement
Contents of Time Extension Requests. The Contractor shall provide with each time extension request Time Extension Request a quantitative demonstration of the impact of the delay on project completion time, based on the Work Progress Schedule. The Contractor shall include with Time Extension Requests a reasonably detailed narrative setting forth:
9.9.3.1 8.9.3.1 The nature of the delay and its cause; the basis of the Contractor’s claim of entitlement to a time extension.
9.9.3.2 8.9.3.2 Documentation of the actual impacts of the claimed delay on the critical path indicated in the Contractor’s Work Progress Schedule, and any concurrent delaysconcurrentdelays.
9.9.3.3 8.9.3.3 Description and documentation of steps taken by the Contractor to mitigate the effect of the claimed delay, including, when appropriate, the modification of the Work Progress Schedule.
Appears in 1 contract
Sources: Standard Agreement
Contents of Time Extension Requests. The Contractor shall provide Provide with each time extension request Time Extension Request a quantitative demonstration of the impact of the delay on project Project completion time, based on the Work Progress Schedule. The Contractor shall include Include with Time Extension Requests a reasonably detailed narrative setting forth:
9.9.3.1 The nature of the delay and its cause; the basis of the Contractor’s claim of entitlement to a time extension.
9.9.3.2 Documentation of the actual impacts of the claimed delay on the critical path indicated in the Contractor’s Work Progress Schedule, and any concurrent delays.
9.9.3.3 Description and documentation of steps taken by the Contractor to mitigate the effect of the claimed delay, including, when appropriate, the modification of the Work Progress Schedule.