CONTRACT/PROJECT CHANGE ORDER PROCESS. For projects involving Technology Implementation services, where frequent and/or multiple minor changes to the project schedule or deliverables are anticipated, the following process may be utilized to effectuate such minor changes without undue project delays (“Change Orders”). Changes to a Contract during its term may incur additional costs and possible delays relative to the project schedule or may result in less cost to the State (for example, the State decides it no longer needs a deliverable in whole or part) or less effort on the part of a selected vendor. A Change Order shall define the effort involved in implementing the change, the total cost or associated savings to the State, of implementing the change, and the effect, if any, of implementing the change on the project schedule. Any change that alters the essential terms of the original contract, including any change that expands or decreases the statement of work, the contract duration, the payment terms and/or the contract maximum amount, shall require a Contract Amendment in accordance with State contracting policies and procedures. Under no circumstances may a Change Order be used where a Contract Amendment is otherwise required pursuant to the Contract Amendments, Approval and Execution process set forth in State Administrative Bulletin 3.5. Change Orders will be developed jointly, and every effort will be made to adhere to the approved Project Plan. The Project Manager for the State and the Project Manager for a Contractor will decide whether a Change Order is necessary. If a Change Order is necessary, the Project Manager for requesting party will prepare a Change Order Request detailing the impacts on scope, schedule, deliverables, resources, and cost. The Change Order Request must be submitted to the non- requesting party for review. The non-requesting party will make its best efforts to either approve or deny the Change Order in writing within (10) business days. In no event shall any delay in the approval or denial of a Change Request constitute a deemed approval by the State. The State will not pay for the effort involved in developing a Change Order. The Contractor shall bear the cost of estimating the cost or savings, time, and Contractor resources required to implement all Change Order Requests forthcoming from the State during the course of the Project. All Change Orders that are mutually agreed upon must: a. be in writing and describe, with specific reference to the applicable section(s) of the contract, what is being added, deleted or otherwise modified; b. be signed by both the State and the Contractor; c. include the original contract number and a sequential Change Order number; d. include Contractor certifications regarding Taxes, Debarment, and Child Support, as detailed in State Administrative Bulletin 3.5, Section XIII(A)(c); and e. be consolidated into a formal Contract Amendment whenever an amendment would otherwise be required by State Administrative Bulletin 3.5.
Appears in 2 contracts
Sources: Technology Services Agreement, Technology Services Agreement
CONTRACT/PROJECT CHANGE ORDER PROCESS. For projects involving Technology Implementation services, where frequent and/or multiple minor changes to the project schedule or deliverables are anticipated, the following process may be utilized to effectuate such minor changes without undue project delays (“Change Orders”). Changes to a Contract during its term may incur additional costs and possible delays relative to the project schedule schedule, or may result in less cost to the State (for example, the State decides it no longer needs a deliverable in whole or part) or less effort on the part of a selected vendorthe Contractor. A Change Order shall define the effort involved in implementing the change, the total cost or associated savings to the State, of implementing the change, and the effect, if any, of implementing the change on the project schedule. Any change that alters the essential terms of the original contract, including any change that expands or decreases the statement of work, the contract duration, the payment terms and/or the contract maximum amount, shall require a Contract Amendment in accordance with State contracting policies and procedures. Under no circumstances may a Change Order be used where a Contract Amendment is otherwise required pursuant to the Contract Amendments, Approval and Execution process set forth in State Administrative Bulletin 3.5. Change Orders will be developed jointly, jointly and every effort will be made to adhere to the approved Project Plan. The Project Manager for the State and the Project Manager for a Contractor will decide whether a Change Order is necessary. If a Change Order is necessary, the Project Manager for requesting party will prepare a Change Order Request detailing the impacts on scope, schedule, deliverables, resources, and cost. The Change Order Request must be submitted to the non- non-requesting party for review. The non-requesting party will make its best efforts to either approve or deny the Change Order in writing within (10) business days. In no event shall any delay in the approval or denial of a Change Request constitute a deemed approval by the State. The State will not pay for the effort involved in developing a Change Order. The Contractor shall bear the cost of estimating the cost or savings, time, and Contractor resources required to implement all Change Order Requests forthcoming from the State during the course of the Project. All Change Orders that are mutually agreed upon must:
a. be in writing and describe, with specific reference to the applicable section(s) of the contract, what is being added, deleted or otherwise modified;
b. be signed by both the State and the Contractor;
c. include the original contract number and a sequential Change Order number;
d. include Contractor certifications regarding Taxes, Debarment, and Child Support, as detailed in State Administrative Bulletin 3.5, Section XIII(A)(c); and
e. be consolidated into a formal Contract Amendment whenever an amendment would otherwise be required by State Administrative Bulletin 3.5.