Common use of Contract Works Clause in Contracts

Contract Works. With regards to contract works claims, the contractor/consultant is responsible for a deductible (excess) of R250 000. • Contractors / consultants may re-insure the deductible

Appears in 4 contracts

Sources: Engineering and Construction Contract, Term Service Contract, Nec 3: Term Service Contract (Tsc)

Contract Works. With regards to contract works claims, the contractor/contractor / consultant is responsible for a deductible (excess) of R250 000. • Contractors / Contractors/consultants may re-insure the deductible

Appears in 2 contracts

Sources: Engineering and Construction Contract, Nec 3: Engineering and Construction Contract (Ecc)

Contract Works. With regards to contract works claims, the contractor/contractor / consultant is responsible for a deductible (excess) of R250 000. ; • Contractors / consultants may should re-insure the deductible.

Appears in 1 contract

Sources: Nec 3: Professional Services Contract (Psc)

Contract Works. 20.1.1 With regards to contract works claims, the contractor/consultant is responsible for a deductible (excess) of R250 000. • . 20.1.2 Contractors / consultants may re-insure the deductible

Appears in 1 contract

Sources: Consultancy Agreement

Contract Works. With regards to contract works claims, the contractor/consultant is responsible for a deductible (excess) of R250 000. ; • Contractors / consultants may should re-insure the deductible.

Appears in 1 contract

Sources: Nec 3: Professional Services Contract (Psc)

Contract Works. With regards to contract works claims, the contractor/contractor / consultant is responsible for a deductible (excess) of R250 000. • Contractors / consultants may re-insure the deductible

Appears in 1 contract

Sources: Engineering and Construction Contract