Common use of Contractor to search cause Clause in Contracts

Contractor to search cause. 17.5.1 The Authority‟s Engineer may instruct the Contractor to examine the cause of any Defect in the Works or part thereof before the expiry of the Defects Liability Period. 17.5.2 In the event any Defect identified under Clause 17.5.1 is attributable to the Contractor, the Contractor shall rectify such Defect within the period specified by the Authority‟s Engineer, and shall bear the cost of the examination and rectification of such Defect.

Appears in 2 contracts

Sources: Engineering, Procurement and Construction Agreement, Construction Contract

Contractor to search cause. 17.5.1 15.5.1 The Authority‟s Authority Engineer may instruct the Contractor to examine the cause of any Defect in the Works or part thereof before the expiry of the Defects Liability Period. 17.5.2 15.5.2 In the event any Defect identified under Clause 17.5.1 15.5.1 is attributable to the Contractor, the Contractor shall rectify such Defect within the period specified by the Authority‟s Authority Engineer, and shall bear the cost of the examination and rectification of such Defect.

Appears in 2 contracts

Sources: Engineering, Procurement and Construction (Epc) Agreement, Engineering, Procurement and Construction (Epc) Agreement

Contractor to search cause. 17.5.1 15.5.1 The Authority‟s Authority’s Engineer may instruct the Contractor to examine the cause of any Defect in the Works or part thereof before the expiry of the Defects Liability Period. 17.5.2 15.5.2 In the event any Defect identified under Clause 17.5.1 15.5.1 is attributable to the Contractor, the Contractor shall rectify such Defect within the period specified by the Authority‟s Authority’s Engineer, and shall bear the cost of the examination and rectification of such Defect.

Appears in 2 contracts

Sources: Engineering, Procurement and Construction Agreement, Engineering, Procurement and Construction Agreement