Correction of Deficiencies after SPSR. If at any time following the SPSR and prior to Intentional Ignition (or in the event of a Terminated Ignition, prior to any subsequent Intentional Ignition), the Satellite fails to meet Exhibit B, Satellite Performance Specification, as may be modified as of such time pursuant to Article 9.1.4, Contractor shall promptly undertake to correct such deficiencies prior to Intentional Ignition (or in the case of a Terminated Ignition, prior to any subsequent Intentional Ignition) and the Contract Delivery schedule set forth in Article 3 shall be extended as necessary to accommodate such corrective actions, and, in the event of a Terminated Ignition, Contractor shall be entitled to such other compensation for such corrections, if any, to the extent and as provided in Article 12.1.