Deficient Performance. Liquidated Damages shall be applied to deficient performance and/or late completion. Parties hereto agree that it is impracticable or extremely difficult to determine actual damages the County shall sustain by reason of delay in performance. Therefore, Two Hundred Fifty Dollars ($250.00) will be deducted and withheld from payments due or to become due to Contractor for each calendar day work is incomplete beyond the scheduled day. Contractor shall be granted extension of time and shall not be assessed Liquidated Damages for delays caused by acts of God.