Common use of Delays by Utility Owners Clause in Contracts

Delays by Utility Owners. 6.8.5.1 Developer shall bear 100% of the risk of Critical Path delays caused by a Utility Owner’s failure to timely comply with the requirements of a Utility Agreement which has been executed by Developer and such Utility Owner.

Appears in 19 contracts

Sources: Development Agreement, Development Agreement, Comprehensive Development Agreement

Delays by Utility Owners. 6.8.5.1 (a) Developer shall bear 100% of the risk of Critical Path delays caused by a Utility Owner’s failure to timely comply with the requirements of a Utility Agreement which has been executed by Developer and such Utility Owner.

Appears in 15 contracts

Sources: Development Agreement, Development Agreement, Development Agreement

Delays by Utility Owners. 6.8.5.1 5.1 Developer shall bear 100% of the risk of Critical Path delays caused by a Utility Owner’s failure to timely comply with the requirements of a Utility Agreement which has been executed by Developer and such Utility Owner.

Appears in 3 contracts

Sources: Comprehensive Development Agreement, Development Agreement, Development Agreement

Delays by Utility Owners. 6.8.5.1 6.8.6.1 Developer shall bear 100% of the risk of Critical Path delays caused by a Utility Owner’s failure to timely comply with the requirements of a Utility Agreement which has been executed by Developer and such Utility Owner.

Appears in 1 contract

Sources: Comprehensive Development Agreement