Common use of Design Basis Clause in Contracts

Design Basis. All steam piping shall be designed for the maximum pressure and temperature design requirements, including transient and upset conditions. The steam piping shall be sized for the pressure drop requirements in order to satisfy plant thermodynamic performance criteria. The hot and cold reheat steam piping systems include provisions for venting of noncondensables and warm-up during startup. In addition, an adequately designed drain system shall be provided to remove condensate during startup and low load operation.

Appears in 3 contracts

Sources: Engineering, Procurement and Construction Services Agreement (Aes Ironwood LLC), Engineering, Procurement and Construction Services Agreement (Aes Ironwood LLC), Engineering, Procurement and Construction Services Agreement (Aes Ironwood LLC)