Design Progress Meetings. Once a design consultant or design-builder is engaged for the project by the Department, the Project Management Contractor shall schedule and participate in periodic design management meetings. Unless otherwise directed by the DGS Project Manager, such meetings should occur every other week (i.e. roughly twice a month). These meetings will be chaired by the DGS Project Manager assigned to the project and a representative of the Client Agency shall be invited to participate. In general, the purpose of these meetings shall be to review the design as it evolves and to provide feedback/input to the design consultant. Unless otherwise directed by the DGS Project Manager, the Project Management Contractor shall keep the minutes of these meetings and shall maintain an action item list of open issues.