Design Schedule. 1.4.1 Within 10 days after execution of this Agreement, or other period agreed with the Contracting Authority, the A/E shall submit, for approval by the Contracting Authority and Owner, a Design Schedule for the performance of the A/E’s Services. 1.4.2 The Design Schedule shall include allowances for reasonable periods required for review and approval of items by the Contracting Authority and Owner, and for approvals of governmental authorities having jurisdiction over the Project. 1.4.3 Unless the Contracting Authority or Owner notify the A/E of objections to the Design Schedule within 30 days of receipt thereof, the Contracting Authority and Owner shall be deemed to have approved the Design Schedule. 1.4.4 The A/E shall coordinate the Design Schedule with the Project Schedule. 1.4.5 The A/E shall not exceed or adjust the Design Schedule after its initial approval without the prior written consent of the Contracting Authority and Owner. 1.4.6 The A/E shall perform its Services in a timely manner consistent with the Project Schedule.
Appears in 8 contracts
Sources: Professional Services, Professional Services, Architect/Engineer Agreement
Design Schedule. 1.4.1 1.5.1 Within 10 ten days after execution of this Agreement, or other period agreed with by the A/E and Contracting Authority, the A/E shall submit, for approval by the Contracting Authority and Owner, a Design Schedule for the performance of the A/E’s Services.
1.4.2 1.5.2 The Design Schedule shall include allowances for reasonable periods required for review and approval of items by the Contracting Authority and Owner, and for approvals of governmental authorities having that have jurisdiction over the Project.
1.4.3 1.5.3 Unless the Contracting Authority or Owner notify the A/E of objections to the Design Schedule within 30 days of receipt thereofafter receiving it, the Contracting Authority and Owner shall be deemed to have approved the Design Schedule.
1.4.4 1.5.4 The A/E shall coordinate the Design Schedule with the Project Schedule.
1.4.5 1.5.5 The A/E shall not exceed or adjust the Design Schedule after its initial approval without the prior written consent of the Contracting Authority and Owner.
1.4.6 1.5.6 The A/E shall perform its Services in a timely manner consistent with the Project Schedule.
Appears in 2 contracts
Sources: Architect/Engineer Agreement, Architect/Engineer Agreement