Development Period Sample Clauses
POPULAR SAMPLE Copied 3 times
Development Period. The Contractor may commence pre-construction activities like utility shifting, boundary wall construction or any other activity assigned to the Contractor by the Authority to enable construction of the Project Highway immediately after signing of the Agreement, to the extent that such work is ready for execution. The Parties agree that these works may be taken up and completed to the extent feasible by the Contractor, before declaration of the Appointed Date, but no claim against the Authority for delay shall survive during this period and that the undertaking of these works by the Contractor shall not count towards the Scheduled Construction Period of the project which starts counting only from the Appointed Date. No construction activity of the Project Highway shall be undertaken during the development period.
10.1 Obligations prior to commencement of Works
(i) Within 20 (twenty) days of the Appointed Date, the Contractor shall:
(a) appoint its representative, duly authorised to deal with the Authority in respect of all matters under or arising out of or relating to this Agreement;
(b) appoint a design director (the “Design Director”) who will head the Contractor’s design unit and shall be responsible for surveys, investigations, collection of data, and preparation of preliminary and detailed designs;
(c) undertake and perform all such acts, deeds and things as may be necessary or required before commencement of Works under and in accordance with this Agreement, the Applicable Laws and Applicable Permits; and
(d) make its own arrangements for quarrying of materials needed for the Project Highway under and in accordance with the Applicable Laws and Applicable Permits.
(ii) The Authority shall, appoint an engineer (the “Authority’s Engineer”) before the Appointed Date to discharge the functions and duties specified in this Agreement, and shall notify to the Contractor the name, address and the date of appointment of the Authority’s Engineerforthwith.
(iii) Work Programme
(A) Within 30 (thirty) days of the Appointed Date, the Contractor shall submit to the Authority and the Authority’s Engineer a work programme (the “Programme”) for organising and carrying out whole of the Works, developed using computerized Critical Path Method (CPM) networking techniques, using the Precedence Diagramming Method (PDM) and shall be present in bar chart and time-scaled network diagram format to a weekly or monthly time scale for review and consent of the Engineer, giving the...
Development Period. 4.1 During the Development Period, the Independent Consultant shall undertake a detailed review of the Drawings to be furnished by the Concessionaire along with supporting data, including the investigations, characteristics of materials from borrow areas and sites and topographical surveys. The Independent Consultant shall complete such review and send its comments/observations to the CHB and the Concessionaire within 15 (fifteen) days of receipt of such Drawings. In particular, such comments shall specify the conformity or otherwise of such Drawings with the Scope of the Project and Specifications and Standards.
4.2 The Independent Consultant shall review any modified Drawings or supporting Documents sent to it by the Concessionaire and furnish its comments within 7 (seven) days of receiving such Drawings or Documents.
Development Period. The Contractor may commence pre-construction activities like utility shifting, boundary wall construction or any other activity assigned to the Contractor by the Authority to enable construction of the Project Highway immediately after signing of the Agreement, to the extent that such work is ready for execution. The Parties agree that these works may be taken up and completed to the extent feasible by the Contractor, before declaration of the Appointed Date, but no claim against the Authority for delay shall survive during this period and that the undertaking of these works by the Contractor shall not count towards the Scheduled Construction Period of the project which starts counting only from the Appointed Date. No construction activity of the Project Highway shall be undertaken during the development period.
Development Period. 2.1 During the Development Period, the Independent Engineer shall undertake a detailed review of the Drawings to be furnished by the Concessionaire along with supporting data, including the geo-technical and hydrological investigations, characteristics of materials from borrow areas and quarry sites, topographical surveys and traffic surveys. The Independent Engineer shall complete such review and send its comments/observations to the Concessioning Authority and the Concessionaire within 15 (fifteen) days of receipt of such drawings. In particular, such comments shall specify the conformity or otherwise of such Drawings with the Scope of the Project and Specifications and Standards.
2.2 The Independent Engineer shall review any modified Drawings or supporting documents sent to it by the Concessionaire and furnish its comments within 7 (seven) days of receiving such Drawings or Documents.
2.3 The Independent Engineer shall review the Drawings sent to it by the Safety Consultant in accordance with Schedule-L and furnish its comments thereon to the Concessioning Authority and the Concessionaire and the Concessionaire within 7 (seven) days of receiving such Drawings. The Independent Engineer shall also review the Safety Report and furnish its comments thereon to the Concessioning Authority within 15 (fifteen) days of receiving such report.
2.4 The Independent Engineer shall review the detailed design, construction methodology, quality assurance procedures and the procurement, engineering and construction time schedule sent to it by the Concessionaire and furnish its comments within 15 (fifteen) days of receipt thereof.
2.5 Upon reference by the Concessioning Authority, the Independent Engineer shall review and comment on the EPC Contract or any other contract for construction, operation and maintenance of the Project, and furnish its comments within 7 (seven) days from receipt of such reference from the Concessioning Authority.
Development Period studies preliminary to the Development project; - planned Drilling; - necessary plant and equipment; - dimensions of structures and other necessary facilities; - proposed professional training programme;
Development Period. The term "Development Period" means the period ------------------ commencing on the date of this Agreement and terminating on the date which is three (3) months after the Completion Date.
Development Period. 2.1 In consideration of Penwest's entering into this Agreement, Mylan shall pay Penwest upon the Effective Date a nonrefundable initial fee of ************.
2.2 As additional inducement to Penwest to enter into this Agreement, Mylan hereby affirms that, other than confidentiality agreements not binding either party to any further agreement, it currently has no agreement or arrangement with any Person other than Penwest for or including the development, design, testing, certification, manufacture or marketing by it or such other Person (or the Affiliate(s) of either) of any controlled-release Nifedipine product that is intended to be essentially bioequivalent to "Procardia XL," and agrees that it will refrain from entering into any such agreement or arrangement (other than such confidentiality agreements) throughout the duration of the Development Period or the period of eighteen months following the date hereof, whichever expires later.
2.3 During the Development Period, each of Penwest and Mylan will exert its continuing best efforts to perform their respective tasks specified in Exhibit , within the estimated time periods there stated, in order to create and produce the Designated Product, and each will cooperate with the other in such efforts. It is understood that the exertion of a party's best efforts will mean that this project will receive a priority at least as high as any of such party's other generic drug development efforts. Each party will, promptly and throughout the Development Period, provide to the other all necessary information in or coming into its possession or reasonably available to it for such purposes. Notwithstanding anything else to the contrary contained herein, nothing shall require either party to disclose confidential information for which such party has an obligation of confidentiality to a third party. Each party understands and agrees that the other does not warrant or commit that the Designated Product will be successfully developed, and neither party shall have any liability or responsibility to the other or to third parties for any such failure of the development process hereunder, except to the extent such failure results from said party's intentional misconduct, negligence, or breach of its duties or obligations as set forth herein.
2.4 Mylan shall be responsible for, and hereby agrees to conduct or arrange for, at Mylan's expense, all testing and studies during the Development Period, CONFIDENTIAL MATERIAL OMITTED AND...
Development Period. During the Development Period, the Independent Consultant shall undertake a detailed review of the Drawings to be furnished by the Concessionaire along with supporting data, including the investigations, characteristics of materials from borrow areas and sites and topographical surveys. The Independent Consultant shall complete such review and send its comments/ observations to the NRDA and the Concessionaire within 15 (fifteen) days of receipt of such Drawings. In particular , such comments shall specify the conformity or otherwise of such Drawings with the Scope of the Project and Specifications and Standards.
Development Period. The Contractor may commence pre-construction activities like utility shifting, boundary wall construction or any other activity assigned to the Contractor by the Authority to enable construction of the Project Highway immediately after signing of the Agreement, to the extent that such work is ready for execution. The Parties agree that these works may be taken up and completed to the extent feasible by the Contractor, before declaration of the Appointed Date, but no claim against the Authority for delay shall survive during this period and that the undertaking of these works by the Contractor shall not count towards the Scheduled Construction Period of the project which starts counting only from the Appointed Date. No construction activity of the Project Highway shall be undertaken during the development period. Bangladesh Border including Dawki Bridge from (Design km 63+530 to km 71+520) design length of 7.99 km in the State of Meghalaya for execution on EPC mode under JICA funding - (Package-V)-Balance Work
Development Period. The successful developer is required to sign the agreement within 3 months from the date of NoA complying with the conditions set out in the tender document and to obtain all requisite approvals including Environmental Clearance within a period of 10 months starting from the date of NoA. The development period shall be 108 months which shall include the period of 10 months for obtaining requisite approvals and said also include the period within which the developer shall allot the housing units/apartments to the end users and sign the lease agreement as set out in the agreement.