Differing Site Conditions. In the event that during the course of the Work CONTRACTOR encounters subsurface or concealed conditions at the Project site which differ materially from those shown on the Contract Documents and from those ordinarily encountered and generally recognized as inherent in work of the character called for in the Contract Documents and Supplementary Conditions; or unknown physical conditions of the Project site, of an unusual nature, which differ materially from that ordinarily encountered and generally recognized as inherent in work of the character called for in the Contract Documents in the locales such as that where the work is to be done, CONTRACTOR shall, within twenty-four (24) hours of their discovery, notify CITY in writing of the existence of the aforesaid conditions. CITY shall, within two (2) business days after receipt of CONTRACTOR's written notice, investigate the site conditions identified by CONTRACTOR. If, in the sole opinion of CITY ENGINEER with the consent of City’s Project Manager, the conditions do materially so differ and cause an increase or decrease in CONTRACTOR's cost of, or the time required for, the performance of any part of the Work, CITY ENGINEER shall recommend an equitable adjustment to the Contract Price, or the Contract Time, or both. If CITY and CONTRACTOR cannot agree on an adjustment in the Contract Price or Contract Time, the adjustment shall be referred to CITY ENGINEER for determination in accordance with the provision for resolving disputes. Should CITY ENGINEER determine that the conditions of the Project site are not so materially different to justify a change in the terms of the Contract, CITY ENGINEER shall so notify CONTRACTOR in writing, stating the reasons, and such determination shall be final and binding upon the parties hereto. No request for an equitable adjustment or change to the Contract Price or Contract Time for differing site conditions shall be allowed if made after the date certified by CITY ENGINEER as the date of substantial completion.
Appears in 9 contracts
Sources: Invitation to Bid, Invitation to Bid, Invitation to Bid
Differing Site Conditions. 16.1 In the event that during the course of the Work CONTRACTOR work the Contractor encounters subsurface or concealed conditions at the Project project site which differ materially from those shown on the Contract Documents and from those ordinarily encountered and generally recognized as inherent in work of the character called for in the Contract Documents and Supplementary Conditionsany supplementary conditions; or unknown physical conditions of the Project project site, of an unusual nature, which differ materially from that ordinarily encountered and generally recognized as inherent in work of the character called for in the Contract Documents in the locales such as that where the work is to be done, CONTRACTOR Contractor shall, within twenty-four (24) hours of their discovery, notify CITY the NMCRA in writing of the existence of the aforesaid conditions. CITY NMCRA shall, within two (2) business days after receipt of CONTRACTOR's Contractor’s written notice, investigate the site conditions identified by CONTRACTORContractor. If, in the sole opinion of CITY ENGINEER with the consent of City’s Project ManagerNMCRA, the conditions do materially so differ and cause an increase or decrease in CONTRACTOR's Contractor’s cost of, or the time required for, the performance of any part of the Work, CITY ENGINEER NMCRA shall recommend an equitable adjustment to the Contract PriceFee, or the Contract TimeTerm, or both. If CITY NMCRA and CONTRACTOR Contractor cannot agree on an adjustment in the Contract Price Fee or Contract TimeTerm, the adjustment shall be referred to CITY ENGINEER City Engineer for determination in accordance with the provision for resolving disputes. Should CITY ENGINEER City Engineer determine that the conditions of the Project project site are not so materially different to justify a change in the terms of the ContractAgreement, CITY ENGINEER City Engineer shall so notify CONTRACTOR Contractor in writing, stating the reasons, and such determination shall be final and binding upon the parties hereto. .
16.2 No request for an equitable adjustment or change to the Contract Price Fee or Contract Time Term for differing site conditions shall be allowed if made after the date certified by CITY ENGINEER as the date of substantial completionSubstantial Completion.
Appears in 4 contracts
Sources: Contractor Agreement, Contractor Agreement, Contractor Agreement
Differing Site Conditions. 1. In the event that during the course of the Work Work, CONTRACTOR encounters subsurface or concealed conditions at the Project job site which differ materially from those shown on the Contract Project Documents and from those ordinarily encountered and generally recognized as inherent in work of the character called for in the Contract Documents and Supplementary Conditions; Project Documents, or unknown physical conditions of the Project site, of an unusual naturenature at the job site, which differ materially from that ordinarily encountered and generally recognized as inherent in work of the character called for in the Contract Documents in Project Documents, CONTRACTOR, without disturbing the locales conditions and before performing any work affected by such as that where the work is to be doneconditions, CONTRACTOR shall, within twenty-four (24) hours of their its discovery, notify CITY in writing the Project Manager of the existence of the aforesaid conditions.
2. CITY The Project Manager shall, within two (2) business days after receipt of CONTRACTOR's written notice, investigate the site conditions identified by CONTRACTOR. If, in the sole opinion of CITY ENGINEER with the consent of City’s Project Manager, the conditions do materially so differ and cause an increase or decrease in CONTRACTOR's cost of, or the time required for, the performance of any part of the Work, CITY ENGINEER whether or not charged as a result of the conditions, CONTRACTOR shall recommend an equitable provide a revised estimate including adjustment to the Contract Project Price, or the Contract Project Time, or both, for the Project Manager’s approval.
3. If CITY the Project Manager and CONTRACTOR cannot agree on an adjustment in the Contract Project Price or Contract Project Time, the adjustment shall be referred to CITY ENGINEER the Contract Administrator for determination in accordance with the provision for resolving disputesfinal determination. Should CITY ENGINEER the Contract Administrator determine that the conditions of the Project site are not so materially different to justify a change in the terms of the ContractProject/NTP, CITY ENGINEER the Contract Administrator shall so notify CONTRACTOR in writing, stating the reasons, and such determination shall be final and binding upon the parties heretohereto after which the CONTRACTOR will be required to proceed with the work without any additional compensation related to such conditions.
4. No request by CONTRACTOR for an equitable adjustment to the Project Price under this provision shall be allowed unless CONTRACTOR has given written notice in strict accordance with the provisions of this Section.
5. No request for an equitable adjustment or change changes to the Contract Project Price or Contract Project Time for differing site conditions shall be allowed if made after the date certified declared by CITY ENGINEER the Contract Administrator, or designee, as the date of substantial completion.
Appears in 1 contract
Sources: Contract for Bridge Repairs
Differing Site Conditions. In the event that during the course of the Work CONTRACTOR Contractor encounters subsurface or concealed conditions at the Project site which differ materially from those shown on the Contract Documents and from those ordinarily encountered and generally recognized as inherent in work of the character called for in the Contract Documents and Supplementary ConditionsDocuments; or unknown physical conditions of the Project site, of an unusual nature, which differ materially from that ordinarily encountered and generally recognized as inherent in work of the character called for in the Contract Documents in Documents, Contractor , without disturbing the locales conditions and before performing any work affected by such as that where the work is to be doneconditions, CONTRACTOR shall, within twentythree (3) days or seventy-four two (2472) hours of their discovery, notify CITY Village and Consultant in writing of the existence of the aforesaid conditions. CITY Consultant and Village shall, within two (2) business days after receipt of CONTRACTORContractor's written notice, investigate the site conditions identified by CONTRACTORContractor. If, in the sole opinion of CITY ENGINEER with the consent of City’s Project ManagerConsultant, the conditions do materially so differ and cause an increase or decrease in CONTRACTORContractor's cost of, or the time required for, the performance of any part of the Work, CITY ENGINEER whether or not charged as a result of the conditions, Consultant shall recommend an equitable adjustment to the Contract Price, or the Contract Time, or both. If CITY Village and CONTRACTOR Contractor cannot agree on an adjustment in the Contract Price or Contract Time, the adjustment shall be referred to CITY ENGINEER Consultant for determination in accordance with the provision for resolving disputesprovisions of Section 12. Should CITY ENGINEER Consultant determine that the conditions of the Project site are not so materially different to justify a change in the terms of the Contract, CITY ENGINEER Consultant shall so notify CONTRACTOR Village and Contractor in writing, stating the reasons, and such determination shall be final and binding upon the parties heretohereto subject to dispute resolution in Section 12. No request by Contractor for an equitable adjustment to the Contract under this provision shall be allowed unless Contractor has given written notice in strict accordance with the provisions of this Section. No request for an equitable adjustment or change to the Contract Price or Contract Time for differing site conditions shall be allowed if made after the date certified by CITY ENGINEER Consultant as the date of substantial completion.
Appears in 1 contract
Sources: Contract
Differing Site Conditions. 1. In the event that during the course of the Work Work, CONTRACTOR encounters subsurface or concealed conditions at the Project job site which differ materially from those shown on the Contract Project Documents and from those ordinarily encountered and generally recognized as inherent in work of the character called for in the Contract Documents and Supplementary Conditions; Project Documents, or unknown physical conditions of the Project site, of an unusual naturenature at the job site, which differ materially from that ordinarily encountered and generally recognized as inherent in work of the character called for in the Contract Documents in Project Documents, CONTRACTOR, without disturbing the locales conditions and before performing any work affected by such as that where the work is to be doneconditions, CONTRACTOR shall, within twenty-four (24) hours of their its discovery, notify CITY in writing the Project Manager of the existence of the aforesaid conditions.
2. CITY The Project Manager shall, within two (2) business days after receipt of CONTRACTOR's written notice, investigate the site conditions identified by CONTRACTOR. If, in the sole opinion of CITY ENGINEER with the consent of City’s Project Manager, the conditions do materially so differ and cause an increase or decrease in CONTRACTOR's cost of, or the time required for, the performance of any part of the Work, CITY ENGINEER whether or not charged as a result of the conditions, CONTRACTOR shall recommend an equitable provide a revised estimate including adjustment to the Contract Project Price, or the Contract Project Time, or both, for the Project Manager’s approval.
3. If CITY the Project Manager and CONTRACTOR cannot agree on an adjustment in the Contract Project Price or Contract Project Time, the adjustment shall be referred to CITY ENGINEER the Contract Administrator for determination in accordance with the provision for resolving disputesfinal determination. Should CITY ENGINEER the Contract Administrator determine that the conditions of the Project site are not so materially different to justify a change in the terms of the ContractProject/NTP, CITY ENGINEER the Contract Administrator shall so notify CONTRACTOR in writing, stating the reasons, and such determination shall be final and binding upon the parties heretohereto after which the CONTRACTOR will be required to proceed with the work without any additional compensation related to such conditions.
4. No request by CONTRACTOR for an equitable adjustment to the Project Price under this provision shall be allowed unless CONTRACTOR has given written notice in strict accordance with the provisions of this Section.
5. No request for an equitable adjustment or change to the Contract Project Price or Contract Project Time for differing site conditions shall be allowed if made after the date certified declared by CITY ENGINEER the Contract Administrator, or designee, as the date of substantial completion.
Appears in 1 contract
Sources: Contract for Miscellaneous Bridge and Structural Repairs
Differing Site Conditions. In the event that during the course of the Work CONTRACTOR encounters subsurface or concealed conditions at the Project site which differ materially from those shown on the Contract Documents and from those ordinarily encountered and generally recognized as inherent in work of the character called for in the Contract Documents and Supplementary Conditions; or unknown physical conditions of the Project site, of an unusual nature, which differ materially from that ordinarily encountered and generally recognized as inherent in work of the character called for in the Contract Documents in the locales such as that where the work is to be done, CONTRACTOR shall, within twenty-four (24) hours of their discovery, notify CITY in writing of the existence of the aforesaid conditions. CITY shall, within two (2) business days after receipt of CONTRACTOR's written notice, investigate the site conditions identified by CONTRACTOR. If, in the sole opinion of CITY ENGINEER with the consent of City’s PROJECT MANAGER or Project Manager’s designee, the conditions do materially so differ and cause an increase or decrease in CONTRACTOR's cost of, or the time required for, the performance of any part of the Work, CITY ENGINEER PROJECT MANAGER shall recommend an equitable adjustment to the Contract Price, or the Contract Time, or both. If CITY and CONTRACTOR cannot agree on an adjustment in the Contract Price or Contract Time, the adjustment shall be referred to CITY ENGINEER PROJECT MANAGER for determination in accordance with the provision for resolving disputes. Should CITY ENGINEER PROJECT MANAGER determine that the conditions of the Project site are not so materially different to justify a change in the terms of the Contract, CITY ENGINEER PROJECT MANAGER shall so notify CONTRACTOR in writing, stating the reasons, and such determination shall be final and binding upon the parties hereto. No request for an equitable adjustment or change to the Contract Price or Contract Time for differing site conditions shall be allowed if made after the date certified by CITY ENGINEER PROJECT MANAGER as the date of substantial completion.
Appears in 1 contract
Sources: Invitation to Bid
Differing Site Conditions. In the event that If during the course of the Work CONTRACTOR Design/Build Firm encounters (1) subsurface or concealed conditions at the Project site which that differ materially from those shown on in the Contract Documents and from those ordinarily encountered and generally recognized as inherent in work of the character called for in the Contract Documents and Supplementary ConditionsContract; or (2) unknown physical conditions of the Project site, of an unusual nature, which differ materially from that ordinarily encountered and generally recognized as inherent in work of the character called for in the Contract Documents in Contract, then Design/Build Firm, without disturbing the locales conditions and before performing any Work affected by such as that where the work is to be doneconditions, CONTRACTOR shall, within twenty-four (24) hours of their discovery, notify CITY Contract Administrator and Design Criteria Professional in writing of the existence of the aforesaid conditions. CITY Design Criteria Professional and Contract Administrator shall, within two (2) business days after receipt of CONTRACTOR's of Design/Build Firm’s written notice, investigate the site conditions identified by CONTRACTORDesign/Build Firm. If, in the sole opinion of CITY ENGINEER with the consent of City’s Project ManagerContract Administrator, the conditions do materially so differ and cause an increase or decrease in CONTRACTOR's Design/Build Firm’s cost of, or the time required for, the performance of any part of the Work, CITY ENGINEER shall whether or not charged as a result of the conditions, Contract Administrator may recommend an equitable adjustment to the Contract Price, or the Contract Time, or both. If CITY Contract Administrator and CONTRACTOR Design/Build Firm cannot agree on an adjustment in the Contract Price or Contract Time, the adjustment shall be referred to CITY ENGINEER Design Criteria Professional for determination in accordance with the provisions of Article 16. No request by Design/Build Firm for an equitable adjustment to the Contract under this provision for resolving disputes. Should CITY ENGINEER determine that the conditions of the Project site are not so materially different to justify a change in the terms of the Contract, CITY ENGINEER shall so notify CONTRACTOR in writing, stating the reasons, and such determination shall be final and binding upon allowed unless Design/Build Firm has given written notice to Contract Administrator in strict accordance with the parties heretoprovisions of this article. No request for an equitable adjustment or change to the Contract Price or Contract Time for differing site conditions shall be allowed if made after the date certified by CITY ENGINEER Contract Administrator as the date of substantial completion.Substantial Completion.
Appears in 1 contract
Sources: Design/Build Contract
Differing Site Conditions. In the event that during the course of the Work CONTRACTOR encounters a. The Contractor shall promptly, and before such conditions are disturbed (except in an emergency) notify SEAPA’s Project Manager in writing of: (1) subsurface or concealed latent physical conditions at the Project site which differ differing materially from those shown on indicated in the Contract Documents contract, and which could not have been discovered by a careful examination of the site, or (2) unknown physical conditions at the site, of an unusual nature, differing materially from those ordinarily encountered and generally recognized as inherent in the work of the character called provided for in the Contract Documents and Supplementary Conditions; contract, which subsurface, latent or unknown physical conditions are not among the risks of performance assumed by the Contractor and which will be considered by the Contractor as a basis for a claim for extra compensation. Changed conditions that occur because of any negligence or inattention on the part of the Contractor, its employees or agents will not be considered eligible for extra payment. SEAPA’s Project siteManager will, of an unusual nature, which differ materially from that ordinarily encountered and generally recognized as inherent in work of the character called for in the Contract Documents in the locales such promptly as that where the work is to be done, CONTRACTOR shall, within twenty-four (24) hours of their discovery, notify CITY in writing of the existence of the aforesaid conditions. CITY shall, within two (2) business days after receipt of CONTRACTOR's written noticepracticable, investigate such conditions and make a finding and determination to the site conditions identified by CONTRACTORContractor. If, in the sole opinion of CITY ENGINEER with the consent of CityIf SEAPA’s Project Manager, the Manager determines that such conditions do materially so differ and cause an increase or decrease in CONTRACTOR's the Contractor’s cost of, or the time required for, the for performance of any part of the WorkWork under the contract, CITY ENGINEER such matters shall recommend be covered by an equitable agreed Change Order. No claim of the Contractor under this section will be allowed unless the Contractor has given the required notice prior to disturbance beyond that necessary to identify the condition. If the Contractor disagrees with SEAPA’s Project Manager’s determination, or if the parties fail to agree upon the adjustment to the Contract Pricebe made, or the Contract Time, or both. If CITY and CONTRACTOR cannot agree on an adjustment in the Contract Price or Contract Time, the adjustment shall be referred to CITY ENGINEER for SEAPA’s Project Manager’s determination in accordance with the provision for resolving disputes. Should CITY ENGINEER determine that the conditions of the Project site are not so materially different to justify a change in the terms of the Contract, CITY ENGINEER shall so notify CONTRACTOR in writing, stating the reasons, and such determination shall will be final and binding upon conclusive unless the parties heretoContractor submits a Notice of Claim to SEAPA in writing. No request Conditions which would have been revealed by a reasonable site inspection shall in no event be considered the basis for a changed condition or granting an equitable adjustment adjustment. In any event, the Contractor shall not be relieved, unless permitted by SEAPA, from its obligation of resuming construction operations pending decision as to the validity of the claim or pending execution of a Change Order to this Contract.
b. Any claim for additional compensation by the Contractor shall not be allowed unless the Contractor has first given the notice required by this Contract. Failure to furnish such notice in a timely manner shall be regarded as a release from and will act as a waiver of the claim. Also, any claim made under this clause shall be limited to the physical location of the construction identified by the Site Plan in the Drawings. In the event that SEAPA and the Contractor are unable to reach an agreement concerning an alleged differing site condition, the Contractor will be required to keep an accurate and detailed record which will indicate the actual cost of the work done under the alleged differing site condition. Failure to keep such a record shall be a bar to any recovery by reason of such alleged differing site conditions. SEAPA shall be given the opportunity to supervise and check the keeping of such records.
c. Any change to statute or regulation shall not form a basis for a claim for additional time or compensation by the Contract Price or Contract Time for differing site conditions shall be allowed if made after the date certified by CITY ENGINEER as the date of substantial completionContractor under this paragraph.
Appears in 1 contract
Differing Site Conditions. In the event that during the course of the Work CONTRACTOR encounters subsurface or concealed conditions at the Project site which differ materially from those shown on the Contract Documents and from those ordinarily encountered and generally recognized as inherent in work of the character called for in the Contract Documents and Supplementary Conditions; or unknown physical conditions of the Project site, of an unusual nature, which differ materially from that ordinarily encountered and generally recognized as inherent in work of the character called for in the Contract Documents in the locales such as that where the work is to be done, CONTRACTOR shall, within twenty-four twenty‐four (24) hours of their discovery, notify CITY in writing of the existence of the aforesaid conditions. CITY shall, within two (2) business days after receipt of CONTRACTOR's written notice, investigate the site conditions identified by CONTRACTOR. If, in the sole opinion of CITY ENGINEER with the consent of City’s Project Manager, the conditions do materially so differ and cause an increase or decrease in CONTRACTOR's cost of, or the time required for, the performance of any part of the Work, CITY ENGINEER shall recommend an equitable adjustment to the Contract Price, or the Contract Time, or both. If CITY and CONTRACTOR cannot agree on an adjustment in the Contract Price or Contract Time, the adjustment shall be referred to CITY ENGINEER for determination in accordance with the provision for resolving disputes. Should CITY ENGINEER determine that the conditions of the Project site are not so materially different to justify a change in the terms of the Contract, CITY ENGINEER shall so notify CONTRACTOR in writing, stating the reasons, and such determination shall be final and binding upon the parties hereto. No request for an equitable adjustment or change to the Contract Price or Contract Time for differing site conditions shall be allowed if made after the date certified by CITY ENGINEER as the date of substantial completion.
Appears in 1 contract
Sources: Construction Contract
Differing Site Conditions. In the event that during the course of the Work CONTRACTOR encounters subsurface Design-Build Entity’s notice to Owner shall be issued by telephone or concealed conditions at the Project site which differ materially from those shown on the Contract Documents in person and from those ordinarily encountered and generally recognized as inherent in work of the character called for in the Contract Documents and Supplementary Conditions; or unknown physical conditions of the Project site, of an unusual nature, which differ materially from that ordinarily encountered and generally recognized as inherent in work of the character called for in the Contract Documents in the locales such as that where the work is to be done, CONTRACTOR shall, followed within twenty-four (24) 24 hours of their discovery, notify CITY in writing of the existence of the aforesaid conditions. CITY shall, within two (2) business days after receipt of CONTRACTOR's thereafter by written notice, providing a brief description of why the condition encountered is considered a Differing Site Condition. Promptly upon receipt of Design-Build Entity’s notice, Owner will investigate the site conditions identified by CONTRACTORconditions. If, during construction, the Design-Build Entity encounters an alleged Differing Site Condition, the Design-Build Entity shall immediately give written notice and may continue work; provided however that the following documents and information shall be submitted on a daily basis:
1. Digital photographs (paper and electronic copy) that detail the Differing Site Conditions;
2. An electronic copy of the pertinent data (e.g. settlement monitoring data, boring logs, dewatering production rates, etc.) for the previous 24 hours;
3. As applicable, sample of soil and groundwater in the sole opinion alleged Differing Site Condition area.
4. Design-Build Entity’s applicable daily reports for each day that the alleged Differing Site Condition exists; and
5. Detailed daily records (which shall include, but not be limited to, labor and equipment), describing the alleged Differing Site Conditions and the impact the Differing Site Conditions are having on the progress of CITY ENGINEER the construction. Immediate written notice shall describe the specific ground conditions encountered and the measures taken to deal with the consent ground conditions. The Design-Build Entity will provide the OR with written notice within 5 business days discovery of City’s Project Manageran Unforeseen and Differing Site Condition. The OR, in conjunction with the Owner and IOR, will promptly investigate the conditions, and if they find that the conditions do so materially so differ differ, or do involve hazardous waste, and cause an a decrease or increase in Design-Build Entity’s Contract Price or decrease in CONTRACTOR's cost of, or the time required for, the performance of Contract Time for any part of the Work, CITY ENGINEER shall the OR will recommend an equitable adjustment to that the Owner issue a Change Order under Section 9 of the Agreement. If it is determined that physical conditions at the site are not materially different from those indicated in Bid Documents or that no change in terms of the Contract PriceDocuments is justified, or the Contract TimeOR will notify Design-Build Entity in writing, or both. If CITY and CONTRACTOR canstating reasons the Design-Build Entity will not agree on be entitled to an adjustment in the Contract Price or Contract Time, the adjustment shall be referred to CITY ENGINEER for determination in accordance with the provision for resolving disputes. Should CITY ENGINEER determine that the conditions Such reasons may include any of the Project site are not so materially different to justify a change in the terms of the Contract, CITY ENGINEER shall so notify CONTRACTOR in writing, stating the reasons, and such determination shall be final and binding upon the parties hereto. No request for an equitable adjustment or change to the Contract Price or Contract Time for differing site conditions shall be allowed if made after the date certified by CITY ENGINEER as the date of substantial completion.following:
Appears in 1 contract
Sources: Design Build Agreement
Differing Site Conditions. In the event that during the course of the Work CONTRACTOR on a Project the Contractor encounters subsurface or concealed conditions at the Project site which differ materially from those shown on in the Contract Documents Contract, and from those ordinarily encountered and generally recognized as inherent in work of the character called for in the Contract Documents Contract, Contractor, without disturbing the conditions and Supplementary Conditions; or unknown physical conditions of the Project sitebefore performing any Work affected by such conditions, of an unusual nature, which differ materially from that ordinarily encountered and generally recognized as inherent in work of the character called for in the Contract Documents in the locales such as that where the work is to be done, CONTRACTOR shall, within twenty-four (24) hours of their its discovery, notify CITY the Project Manager and/or Consultant in writing of the existence of the aforesaid conditions. CITY Project Manager or the Consultant shall, within two (2) business days after receipt of CONTRACTORContractor's written notice, investigate the site conditions identified by CONTRACTORContractor. If, in the sole opinion of CITY ENGINEER with Project Manager or the consent of City’s Project ManagerConsultant, the conditions do materially so differ and cause an increase or decrease in CONTRACTORContractor's cost of, or the time required for, the performance of any part of the Work, CITY ENGINEER whether or not charged as a result of the conditions, Project Manager or Consultant shall recommend an equitable adjustment to cost of the Contract Price, Work or the Contract Timetime to complete the Work, or both. If CITY the Project Manager and CONTRACTOR Contractor cannot agree on an adjustment in the Contract Price or and/or Contract Time, the adjustment shall be referred to CITY ENGINEER the Town’s Procurement Manager for determination in accordance with the provision for resolving disputesdetermination. Should CITY ENGINEER the Town’s Procurement Manager determine that the conditions of the Project site are not so materially different to justify a change in the terms of the Contract, CITY ENGINEER the Director shall so notify CONTRACTOR the Project Manager, Consultant, and Contractor in writing, stating the reasons, and such determination shall be final and binding upon the parties hereto. No request by Contractor for an equitable adjustment to the Contract under this provision shall be allowed unless Contractor has given written notice in strict accordance with the provisions of this Article. No request for an equitable adjustment or change to the Contract Price or Contract Time for differing site conditions shall be allowed if made after the date certified by CITY ENGINEER Consultant or Project Manager as the date of substantial completion.
Appears in 1 contract
Sources: Contract for Construction Services
Differing Site Conditions. In the event that during the course of the Work CONTRACTOR Contractor encounters subsurface or concealed conditions at the Project site which differ materially from those shown on the Contract Documents and from those ordinarily encountered and generally recognized as inherent in work of the character called for in the Contract Documents and Supplementary ConditionsDocuments; or unknown physical conditions of the Project site, of an unusual nature, which differ materially from that ordinarily encountered and generally recognized as inherent in work of the character called for in the Contract Documents in Documents, Contractor , without disturbing the locales conditions and before performing any work affected by such as that where the work is to be doneconditions, CONTRACTOR shall, within twenty-four (24) hours of their discovery, notify CITY Village and Consultant in writing of the existence of the aforesaid conditions. CITY Consultant and Village shall, within two (2) business days after receipt of CONTRACTORContractor's written notice, investigate the site conditions identified by CONTRACTORContractor. If, in the sole opinion of CITY ENGINEER with the consent of City’s Project ManagerConsultant, the conditions do materially so differ and cause an increase or decrease in CONTRACTORContractor's cost of, or the time required for, the performance of any part of the Work, CITY ENGINEER whether or not charged as a result of the conditions, Consultant shall recommend an .an equitable adjustment to the Contract Price, or the Contract Time, or both. If CITY Village and CONTRACTOR Contractor cannot agree on an adjustment in the Contract Price or Contract Time, the adjustment shall be referred to CITY ENGINEER Consultant for determination in accordance with the provision for resolving disputesprovisions of Section 12. Should CITY ENGINEER Consultant determine that the conditions of the Project site are not so materially different to justify a change in the terms of the Contract, CITY ENGINEER Consultant shall so notify CONTRACTOR Village and Contractor in writing, stating the reasons, and such determination shall be final and binding upon the parties hereto. No request by Contractor for an equitable adjustment to the Contract under this provision shall be allowed unless Contractor has given written notice in strict accordance with the provisions of this Section. No request for an equitable adjustment or change to the Contract Price or Contract Time for differing site conditions shall be allowed if made after the date certified by CITY ENGINEER Consultant as the date of substantial completion.
Appears in 1 contract
Sources: Contract
Differing Site Conditions. In the event that during the course of the Work CONTRACTOR work, ▇▇▇▇ encounters an underground utility that was not shown on the CONTRACT DOCUMENTS; or subsurface or concealed conditions at the Project project site which differ materially from those shown on the Contract Documents CONTRACT DOCUMENTS and from those ordinarily encountered and generally recognized as inherent in work of the character called for in the Contract Documents and Supplementary ConditionsCONTRACT DOCUMENTS; or unknown physical conditions of the Project PROJECT site, of an unusual nature, which differ materially from that ordinarily encountered and generally recognized as inherent in work of the character called for in the Contract Documents in CONTRACT DOCUMENTS, ▇▇▇▇ without disturbing the locales conditions and before performing any work affected by such as that where the work is to be doneconditions, CONTRACTOR shall, within twenty-four (24) hours of no later than 9:00 a.m. the next day after their discovery, notify CITY CONSULTANT in writing of the existence of the aforesaid conditions. CITY CONSULTANT shall, within two (2) one business days day after receipt of CONTRACTOR's ▇▇▇▇’▇ written notice, investigate the site conditions identified by CONTRACTORthe CMAR. If, in the sole opinion of CITY ENGINEER with the consent of City’s Project ManagerCONSULTANT, the conditions do materially so differ and cause an increase or decrease in CONTRACTOR's ▇▇▇▇’▇ cost of, or the time required for, for the performance of any part of the Workwork, CITY ENGINEER whether or not charged as a result of the conditions, CONSULTANT shall recommend an equitable adjustment to the Contract PriceCONTRACT PRICE, or the Contract TimeCONTRACT TIME, or both, which is subject to written approval by the PROJECT MANAGER. If CITY CONSULTANT and CONTRACTOR CMAR cannot agree on an adjustment in the Contract Price CONTRACT PRICE or Contract TimeCONTRACT TIME, the adjustment shall be referred to CITY ENGINEER for determination determined by the CONSULTANT in accordance with Article 30. No request by CMAR for an equitable adjustment or change to the CONTRACT PRICE or CONTRACT TIME under this provision for resolving disputes. Should CITY ENGINEER determine that the conditions of the Project site are not so materially different to justify a change in the terms of the Contract, CITY ENGINEER shall so notify CONTRACTOR in writing, stating the reasons, and such determination shall be final allowed unless the CMAR has given written notice within 30 days from when the CMAR knew or should have known of such conditions and binding upon the parties heretowritten notice shall detail the facts relating to such request. No request for an equitable adjustment or change to the Contract Price CONTRACT PRICE or Contract Time CONTRACT TIME for differing different site conditions shall be allowed if made after the date certified by CITY ENGINEER CONSULTANT as the date of substantial completionSUBSTANTIAL COMPLETION.
Appears in 1 contract
Differing Site Conditions. In the event that 34.1. If during the course progress of the Work CONTRACTOR work, the Contractor encounters (1) subsurface or concealed conditions at the Project project site which that differ materially from those shown on indicated in the Contract Documents and Project Documents; or (2)unknown physical conditions of the project site an unusual nature, differing materially from those ordinarily encountered and generally recognized as inherent in the work of the character called provided for in the Contract Documents and Supplementary Conditions; or unknown physical conditions of Project Documents, are encountered at the Project site, of an unusual naturethe Contractor, which differ materially from that ordinarily encountered without disturbing the conditions and generally recognized as inherent in before performing any work of the character called for in the Contract Documents in the locales affected by such as that where the work is to be doneconditions, CONTRACTOR shall, within twenty-four (24) hours of their discovery, notify CITY the Project Manager in writing of the existence of the aforesaid conditions.
34.2. CITY The Project Manager shall, within two (2) business days after receipt of CONTRACTOR's Contractor’s written notice, investigate the site conditions identified by CONTRACTORContractor. If, in the sole opinion of CITY ENGINEER with the consent of City’s Project Manager, the conditions do materially so differ and cause an increase or decrease in CONTRACTOR's Contractor’s cost of, or the time required for, the performance of any part of the Work, CITY ENGINEER shall whether or not charged as a result of the conditions, Project Manager may recommend an equitable adjustment to the Contract Price, or the Contract Time, or both.
34.3. If CITY the Project Manager and CONTRACTOR the Contractor cannot agree on an adjustment in the Contract Price project price or Contract Timeproject time, the adjustment shall be referred to CITY ENGINEER the Contract Administrator for determination in accordance with the provision for resolving disputes. Should CITY ENGINEER determine that the conditions provisions of the Project site are not so materially different RESOLUTION OF DISPUTES SECTION. No request by Contractor for an equitable adjustment to justify a change in the terms of the Contract, CITY ENGINEER shall so notify CONTRACTOR in writing, stating the reasons, and such determination this Contract under this provision shall be final and binding upon allowed unless Contractor has given written notice to Contract Administrator in strict accordance with the parties heretoprovisions of this article. No request for an equitable adjustment or change to the Contract Price project price or Contract Time project time for differing site conditions shall be allowed if made after the date certified by CITY ENGINEER Contract Administrator as the date of substantial completionSubstantial Completion.
34.4. No request by the Contractor for an equitable adjustment to the Contract under this provision shall be allowed unless the Contractor has given written notice in strict accordance with the provisions of this Article.
34.5. No request for an equitable adjustment or change to the project’s price or project time for differing site conditions shall be allowed if made after Final Acceptance of the project.
Appears in 1 contract
Sources: Maintenance and Repair Agreement
Differing Site Conditions. 16.1 In the event that during the course of the Work CONTRACTOR work the Contractor encounters subsurface or concealed conditions at the Project project site which differ materially from those shown on the Contract Documents and from those ordinarily encountered and generally recognized as inherent in work of the character called for in the Contract Documents and Supplementary Conditionsany supplementary conditions; or unknown physical conditions of the Project project site, of an unusual nature, which differ materially from that ordinarily encountered and generally recognized as inherent in work of the character called for in the Contract Documents in the locales such as that where the work is to be done, CONTRACTOR Contractor shall, within twenty-four (24) hours of their discovery, notify CITY the HBCRA in writing of the existence of the aforesaid conditions. CITY HBCRA shall, within two (2) business days after receipt of CONTRACTOR's Contractor’s written notice, investigate the site conditions identified by CONTRACTORContractor. If, in the sole opinion of CITY ENGINEER with the consent of City’s Project ManagerHBCRA, the conditions do materially so differ and cause an increase or decrease in CONTRACTOR's Contractor’s cost of, or the time required for, the performance of any part of the Work, CITY ENGINEER HBCRA shall recommend an equitable adjustment to the Contract PriceFee, or the Contract TimeTerm, or both. If CITY HBCRA and CONTRACTOR Contractor cannot agree on an adjustment in the Contract Price Fee or Contract TimeTerm, the adjustment shall be referred to CITY ENGINEER the City Engineer for determination in accordance with the provision for resolving disputes. Should CITY ENGINEER the City Engineer determine that the conditions of the Project project site are not so materially different to justify a change in the terms of the ContractAgreement, CITY ENGINEER the City Engineer shall so notify CONTRACTOR Contractor in writing, stating the reasons, and such determination shall be final and binding upon the parties hereto. .
16.2 No request for an equitable adjustment or change to the Contract Price Fee or Contract Time Term for differing site conditions shall be allowed if made after the date certified by CITY ENGINEER as the date of substantial completionSubstantial Completion.
Appears in 1 contract
Sources: Contractor Agreement