Upon encountering Sample Clauses

The 'Upon encountering' clause establishes specific actions or procedures that must be followed when a particular event, condition, or circumstance arises during the course of an agreement or process. For example, this clause might require a party to notify the other party, pause certain activities, or implement contingency measures if a defined issue or obstacle is encountered. Its core practical function is to ensure that both parties are prepared to respond appropriately to unforeseen situations, thereby minimizing disruption and clarifying responsibilities in the face of unexpected developments.
Upon encountering a Differing Site Condition, Design-Builder shall provide prompt written notice to Department of such condition, which notice shall not be later than fourteen (14) days after such condition has been encountered. Design-Builder shall, to the extent reasonably possible, provide such notice before the Differing Site Condition has been substantially disturbed or altered.
Upon encountering a Differing Site Condition, Design-Builder shall provide prompt written notice to Department of such condition, which notice shall not be later than fourteen (14)
Upon encountering a Differing Site Condition, JOC Contractor shall provide prompt written notice to City of such condition, which notice shall not be later than seven (7) days after such condition has been encountered. JOC Contractor shall, to the extent reasonably possible, provide such notice before the Differing Site Condition has been substantially disturbed or altered.
Upon encountering a Differing Site Condition, Construction Manager at Risk shall provide prompt written notice to Owner’s Representative of such condition, which notice shall not be later than three (3) days after such condition has been encountered. Construction Manager at Risk shall, to the extent reasonably possible, provide such notice before the Differing Site Condition has been substantially disturbed or altered.
Upon encountering a Differing Site Condition, the Contractor shall provide prompt written notice to the Authority of such condition, which notice shall not be later than seven (7) Days after such condition has been encountered and before the Differing Site Condition has been substantially disturbed or altered. The Contractor waives any right to an adjustment in the Contract Time or the Contract Price for a Differing Site Condition unless the Contractor provides timely written notice as required under this Section.

Related to Upon encountering

  • Payment Processing Citizens may require any other information from Vendor that Citizens deems necessary to verify any compensation request placed under this Agreement and Vendor agrees that it will provide such information as reasonably requested by Citizens. Payment shall be due net thirty (30) calendar days of Citizens’ actual receipt of a complete and undisputed invoice. Where a submitted invoice is incomplete, such as not containing the information described in this Section, Citizens will return the incomplete invoice to Vendor for correction within thirty (30) calendar days of Citizens’ actual receipt of such invoice. Where Citizens reasonably disputes any part of a complete invoice, such as the amount of the compensation request, Citizens shall pay any undisputed portion of the invoiced amount within (30) calendar days of Citizens’ actual receipt of the complete invoice and will describe the basis for the disputed portion of the invoiced amount. Where Vendor disagrees with Citizens dispute of any invoice, the Parties shall seek to resolve the dispute in accordance with the Dispute Resolution Process further described in this Agreement. In no case shall Citizens be subject to late payment interest charges where Vendor has submitted an incomplete invoice or where Citizens has reasonably disputed an invoice. Where Vendor fails to submit an invoice within twelve (12) calendar months of the Services for which compensation is being requested, Vendor acknowledges and agrees that any payment due for such Services is forfeited by Vendor for its failure to timely submit an invoice.

  • Equipment Procurement If responsibility for construction of the Connecting Transmission Owner’s Attachment Facilities or System Upgrade Facilities or System Deliverability Upgrades is to be borne by the Connecting Transmission Owner, then the Connecting Transmission Owner shall commence design of the Connecting Transmission Owner’s Attachment Facilities or System Upgrade Facilities or System Deliverability Upgrades and procure necessary equipment as soon as practicable after all of the following conditions are satisfied, unless the Developer and Connecting Transmission Owner otherwise agree in writing: 5.5.1 NYISO and Connecting Transmission Owner have completed the Interconnection Facilities Study pursuant to the Interconnection Facilities Study Agreement; 5.5.2 The NYISO has completed the required cost allocation analyses, and Developer has accepted his share of the costs for necessary System Upgrade Facilities and System Deliverability Upgrades in accordance with the provisions of Attachment S of the NYISO OATT; 5.5.3 The Connecting Transmission Owner has received written authorization to proceed with design and procurement from the Developer by the date specified in Appendix B hereto; and 5.5.4 The Developer has provided security to the Connecting Transmission Owner in accordance with Article 11.5 by the dates specified in Appendix B hereto.

  • Stop Payment Any instruction to stop payment of an Instrument drawn on the Account must be in writing and signed by one or more Authorized Signatories and/or Authorized Users, in accordance with the signing authority on the Account. On receiving a stop payment instruction of an Instrument drawn on the Account, the Financial Institution will: a) use reasonable diligence to comply with the stop payment, but b) not be liable to the Depositor or any other person by reason of complying with, or failing to comply with, the stop payment, whether the Financial Institution is negligent, wilfully negligent, or otherwise.

  • Configuration Management The Contractor shall maintain a configuration management program, which shall provide for the administrative and functional systems necessary for configuration identification, control, status accounting and reporting, to ensure configuration identity with the UCEU and associated cables produced by the Contractor. The Contractor shall maintain a Contractor approved Configuration Management Plan that complies with ANSI/EIA-649 2011. Notwithstanding ANSI/EIA-649 2011, the Contractor’s configuration management program shall comply with the VLS Configuration Management Plans, TL130-AD-PLN-010-VLS, and shall comply with the following:

  • Network Interconnection Architecture Each Party will plan, design, construct and maintain the facilities within their respective systems as are necessary and proper for the provision of traffic covered by this Agreement. These facilities include but are not limited to, a sufficient number of trunks to the point of interconnection with the tandem company, and sufficient interoffice and interexchange facilities and trunks between its own central offices to adequately handle traffic between all central offices within the service areas at a P.01 grade of service or better. The provisioning and engineering of such services and facilities will comply with generally accepted industry methods and practices, and will observe the rules and regulations of the lawfully established tariffs applicable to the services provided.