Common use of DISPUTES REGARDING CHANGES Clause in Contracts

DISPUTES REGARDING CHANGES. ‌ 7.4.1 Provided that District pays to Contractor all undisputed sums due under the Contract Documents for Work performed under Change Orders, Contractor shall not delay, slow, interrupt, or suspend the performance of any Work or any Change because of a dispute between the parties with respect to an adjustment in the Contract Sum or Contract Time.

Appears in 2 contracts

Sources: Standard Construction Contract, Construction Contract