Donor Coordination. The Electricity Generation Project has and will continue to benefit from coordination among the Parties and other donors. Donors who are currently working on electricity generation include, among others: (1) the World Bank and the EU, which are funding updates to existing feasibility studies for hydroelectric plants along the Oueme River; and (2) the Islamic Development Bank, which is considering funding a thermal generation plant at the ▇▇▇▇▇ ▇▇▇▇▇ site in Cotonou. A Communauté Electrique du Bénin (“CEB”) hydropower plant currently is under development at Adjarala on the Benin-Togo border, to be funded through the China Export-Import Bank. This plant is anticipated to provide power to CEB, which in turn will supply it to SBEE and to the Compagnie Energie Electrique du Togo.