Draft and Final Deliverable. 1) The Engineer shall produce a draft and final report of wetland determinations and delineations. The draft report must be submitted to the State for review and approval by the State and USACE. In the final report, address State and USACE comments from the draft report. The revised final report must be delivered to the State within 30 days of receipt of comments from the State or USACE. 2) The location of all sites, cities, villages, highways, rivers and other features or place names discussed in the text and situated in the project locale must be shown on the appropriate figure. All tables, figures and maps must have a number, title, appropriate explanatory note and a source reference. In addition, where applicable, figures and all maps must display a title, north arrow, scale, legend and source reference. 3) The report must be in the following format: a) Cover Sheet In accordance with the State’s NEPA MOU, on the cover page of each biological evaluation or assessment, historic properties or cultural resources report, section 4(f) DocuSign Envelope ID: B4E47CBB-54AA-4467-B86B-B1C47B94F45E evaluation, or other analyses prepared under the authority granted by the MOU, the Engineer shall insert the following language in a way that is conspicuous to the reader or include in a CE project record: "The environmental review, consultation, and other actions required by applicable Federal environmental laws for this project are being, or have been, carried-out by TxDOT pursuant to 23 U.S.C. 327 and a Memorandum of Understanding dated December 16, 2014, and executed by FHWA and TxDOT." b) Introduction i. Who authorized the wetland delineation. ii. Why the wetland delineation is being done. iii. Location of site (USGS 7.5’ Map). iv. Date of field visit(s). v. Identification of delineators.
Appears in 1 contract
Sources: Contract for Engineering Services
Draft and Final Deliverable. 1) The Engineer shall produce a draft and final report of wetland determinations and delineations. The draft report must will be submitted to the State for review and approval by the State and USACE. In the final report, address State and USACE comments from the draft report. The revised final report must shall be delivered to the State within 30 days of receipt of comments from the State or USACE.
2) The location of all sites, cities, villages, highways, rivers and other features or place names discussed in the text and situated in the project locale must shall be shown on the appropriate figure. All tables, figures and maps must shall have a number, title, appropriate explanatory note and a source reference. In addition, where applicable, figures and all maps must shall display a title, north arrow, scale, legend and source reference.
3) The report must shall be in the following format:
a) Cover Sheet In accordance with the State’s NEPA MOU, on the cover page of each biological evaluation or assessment, historic properties or cultural resources report, section 4(f) DocuSign Envelope ID: B4E47CBB-54AA-4467-B86B-B1C47B94F45E evaluation, or other analyses prepared under the authority granted by the MOU, the Engineer shall insert the following language in a way that is conspicuous to the reader or include in a CE project record: "The environmental review, consultation, and other actions required by applicable Federal environmental laws for this project are being, or have been, carried-out by TxDOT pursuant to 23 U.S.C. 327 and a Memorandum of Understanding dated December 16, 2014, and executed by FHWA and TxDOT."
b) Introduction
i. Who authorized the wetland delineation.
ii. Why the wetland delineation is being done.
iii. Location of site (USGS 7.5’ Map).
iv. Date of field visit(s).
v. Identification of delineators.. DocuSign Envelope ID: 96ECF328-ADFC-48E2-AAEF-44272BE1E265
c) Methods
Appears in 1 contract
Sources: Contract for Engineering Services