Drawings and Documents. 4.1 The Independent Engineer shall undertake a detailed review of the Drawings to be furnished by the Developer. The Independent Engineer shall complete such review and send its comments/observations and the Developer within 15 (fifteen) days of receipt of such Drawings. In particular, such comments shall specify the conformity or otherwise of such Drawings with the Scope of the Project and Specifications and Standards. 4.2 The Independent Engineer shall review any modified Drawings or supporting Documents sent to it by the Developer and furnish its comments within 7 (seven) days of receiving such Drawings or Documents. 4.3 The Independent Engineer shall review the detailed design, construction methodology, quality assurance procedures and the procurement, engineering and construction time schedule sent to it by the Developer and furnish its comments within 15 (fifteen) days of receipt thereof.
Appears in 2 contracts
Sources: Construction Agreement, Construction Agreement