Common use of Duration of Work Clause in Contracts

Duration of Work. 11.1. The SPP shall be installed within a maximum of 24 (twenty-four) months for SPP with a capacity of less than 100 MWe and within a maximum of 36 (thirty-six) months for SPP with a capacity of more than 100 MWe, from the date when the Generation License is obtained and shall be operated in accordance with the provisions of the Specifications, Contract and relevant legislation 11.2. The Auction Winner agrees and undertakes that it will not claim any compensation from the Contracting Authority if the Work is not completed for any reason within the periods specified in the Specifications and Contract.

Appears in 2 contracts

Sources: Draft Contract for Renewable Energy Resource Zone (Rez SPP 2024), Contract for Renewable Energy Resource Zone (Rez SPP 2024)