Economically Driven Projects. The determination that a transmission addition or upgrade is needed to promote economic efficiency shall be made in any of the following ways: 3.2.1.1.1 If the Participating TO or any party questions the economic need for the project (except where the Project Sponsor commits to pay the full cost of construction) the proposal will be submitted to the ISO ADR Procedures for resolution. 3.2.1.1.2 Where a Project Sponsor other than the Participating TO commits to pay the full cost of construction of a transmission addition or upgrade and its operation, and demonstrates to the ISO financial capability to pay those costs, such commitment and demonstration shall be sufficient to demonstrate need. To ensure that the Project Sponsor is financially able to pay the costs of the project to be constructed by the Participating TO, the Participating TO may require (1) a demonstration of creditworthiness (e.g. an appropriate credit rating), or (2) sufficient security in the form of an unconditional and irrevocable letter of credit or other similar security sufficient to meet its responsibilities and obligations for the full costs of the transmission addition or upgrade. 3.2.1.1.3 Where a Project Sponsor asserts that a transmission addition or upgrade is economically beneficial, but that Project Sponsor is unwilling to commit to pay the full cost of the addition or upgrade; where (1) the proposed transmission expansion or upgrade was submitted to the Participating TO but was not included in the transmission expansion plan of that Participating TO in accordance with Section 3.2.2 or (2) the operation date of the planned expansion is not acceptable to the ISO or the Project Sponsor or (3) the Participating TO unreasonably delays implementing or subsequently decides not to proceed with the project, the Project Sponsor may submit its proposal to the ISO ADR Procedure for determination of need. A determination of need shall be made as follows: 3.2.1.1.3.1 The Project Sponsor shall include in its proposal a showing: (1) that the economic benefits of the proposed transmission addition or upgrade are expected to exceed its costs (giving consideration to any reasonable alternatives to the construction of transmission additions or upgrades), and (2) a proposed pricing methodology for the transmission upgrades that, to the extent practicable, assigns the costs of the planned upgrades to the beneficiaries in proportion to their net benefits. 3.2.1.1.3.2 If neither any Market Participant nor the ISO disputes the Project Sponsor’s showing, then the proposal is determined to be needed. 3.2.1.1.3.3 If any Market Participant or the ISO disputes the Project Sponsor’s showing, then if the proposed transmission addition or upgrade is determined to be needed, the disputing Market Participant, the ISO, or the Project Sponsor may submit to resolution through the ISO ADR Procedure the issues of (1) whether the transmission addition or upgrade is needed on the ground that its economic benefits exceed its costs, (2) whether the beneficiaries of the transmission addition or upgrade can reasonably be identified, and (3) if so, the identity of those beneficiaries and their respective net benefits. If a Market Participant fails to raise through the ISO ADR Procedure a dispute as to whether a proposed transmission addition or upgrade is needed, or as to the identity, if any, of the beneficiary, then the Market Participant shall be deemed to have waived its right to raise such dispute at a later date. The determination under the ISO ADR Procedure as to whether the transmission addition or upgrade is needed and the identity, if any, of the beneficiaries, including any determination by FERC or on appeal of a FERC determination in accordance with that process, shall be final.
Appears in 1 contract
Sources: Transmission Control Agreement
Economically Driven Projects. The determination that a transmission addition or upgrade is needed to promote economic efficiency shall be made in any of the following ways:
3.2.1.1.1 If the Participating TO or any party questions the economic need for the project (except where the Project Sponsor commits to pay the full cost of construction) the proposal will be submitted to the ISO ADR Procedures for resolution.
3.2.1.1.2 Where a Project Sponsor other than the Participating TO commits to pay the full cost of construction of a transmission addition or upgrade and its operation, and demonstrates to the ISO financial capability to pay those costs, such commitment and demonstration shall be sufficient to demonstrate need. To ensure that the Project Sponsor is financially able to pay the costs of the project to be constructed by the Participating TO, the Participating TO may require (1) a demonstration of creditworthiness (e.g. an appropriate credit rating), or (2) sufficient security in the form of an unconditional and irrevocable letter of credit or other similar security sufficient to meet its responsibilities and obligations for the full costs of the transmission addition or upgrade.
3.2.1.1.3 Where a Project Sponsor asserts that a transmission addition or upgrade is economically beneficial, but that Project Sponsor is unwilling to commit to pay the full cost of the addition or upgrade; ¡ where (1) the proposed transmission expansion or upgrade was submitted to the Participating TO but was not included in the transmission expansion plan of that Participating TO in accordance with Section 3.2.2 or (2) the operation date of the planned expansion is not acceptable to the ISO or the Project Sponsor or (3) the Participating TO unreasonably delays implementing or subsequently decides not to proceed with the project, the Project Sponsor may submit its proposal to the ISO ADR Procedure for determination of need. A determination of need shall be made as follows:Section
3.2.1.1.3.1 The Project Sponsor shall include in its proposal a showing: (1) that the economic benefits of the proposed transmission addition or upgrade are expected to exceed its costs (giving consideration to any reasonable alternatives to the construction of transmission additions or upgrades), and (2) a proposed pricing methodology for the transmission upgrades that, to the extent practicable, assigns the costs of the planned upgrades to the beneficiaries in proportion to their net benefits.
3.2.1.1.3.2 If neither any Market Participant nor the ISO disputes the Project Sponsor’s 's showing, then the proposal is determined to be needed.
3.2.1.1.3.3 If any Market Participant or the ISO disputes the Project Sponsor’s 's showing, then if the proposed transmission addition or upgrade is determined to be needed, the disputing Market Participant, the ISO, or the Project Sponsor may submit to resolution through the ISO ADR Procedure the issues of (1) whether the transmission addition or upgrade is needed on the ground that its economic benefits exceed its costs, (2) whether the beneficiaries of the transmission addition or upgrade can reasonably be identified, and (3) if so, the identity of those beneficiaries and their respective net benefits. If a Market Participant fails to raise through the ISO ADR Procedure a dispute as to whether a proposed transmission addition or upgrade is needed, or as to the identity, if any, of the beneficiary, then the Market Participant shall be deemed to have waived its right to raise such dispute at a later date. The determination under the ISO ADR Procedure as to whether the transmission addition or upgrade is needed and the identity, if any, of the beneficiaries, including any determination by FERC or on appeal of a FERC determination in accordance with that process, shall be final.and
Appears in 1 contract
Sources: Transmission Control Agreement
Economically Driven Projects. The determination that a transmission addition or upgrade is needed to promote economic efficiency shall be made in any of the following ways:
3.2.1.1.1 If the Participating TO or any party questions the economic need for the project (except where the Project Sponsor commits to pay the full cost of construction) the proposal will be submitted to the ISO ADR Procedures for resolution.
3.2.1.1.2 Where a Project Sponsor other than the Participating TO commits to pay the full cost of construction of a transmission addition or upgrade and its operation, and demonstrates to the ISO financial capability to pay those costs, such commitment and demonstration shall be sufficient to demonstrate need. To ensure that the Project Sponsor is financially able to pay the costs of the project to be constructed by the Participating TO, the Participating TO may require (1) a demonstration of creditworthiness (e.g. an appropriate credit rating), or (2) sufficient security in the form of an unconditional and irrevocable letter of credit or other similar security sufficient to meet its responsibilities and obligations for the full costs of the transmission addition or upgrade.
3.2.1.1.3 Where a Project Sponsor asserts that a transmission addition or upgrade is economically beneficial, but that Project Sponsor is unwilling to commit to pay the full cost of the addition or upgrade; where (1) the proposed transmission expansion or upgrade was submitted to the Participating TO but was not included in the transmission expansion plan of that Participating TO in accordance with Section 3.2.2 or (2) the operation date of the planned expansion is not acceptable to the ISO or the Project Sponsor or (3) the Participating TO unreasonably delays implementing or subsequently decides not to proceed with the project, the Project Sponsor may submit its proposal to the ISO ADR Procedure for determination of need. A determination of need shall be made as follows:Section
3.2.1.1.3.1 The Project Sponsor shall include in its proposal a showing: (1) that the economic benefits of the proposed transmission addition or upgrade are expected to exceed its costs (giving consideration to any reasonable alternatives to the construction of transmission additions or upgrades), and (2) a proposed pricing methodology for the transmission upgrades that, to the extent practicable, assigns the costs of the planned upgrades to the beneficiaries in proportion to their net benefits.
3.2.1.1.3.2 If neither any Market Participant nor the ISO disputes the Project Sponsor’s showing, then the proposal is determined to be needed.
3.2.1.1.3.3 If any Market Participant or the ISO disputes the Project Sponsor’s showing, then if the proposed transmission addition or upgrade is determined to be needed, the disputing Market Participant, the ISO, or the Project Sponsor may submit to resolution through the ISO ADR Procedure the issues of (1) whether the transmission addition or upgrade is needed on the ground that its economic benefits exceed its costs, (2) whether the beneficiaries of the transmission addition or upgrade can reasonably be identified, and (3) if so, the identity of those beneficiaries and their respective net benefits. If a Market Participant fails to raise through the ISO ADR Procedure a dispute as to whether a proposed transmission addition or upgrade is needed, or as to the identity, if any, of the beneficiary, then the Market Participant shall be deemed to have waived its right to raise such dispute at a later date. The determination under the ISO ADR Procedure as to whether the transmission addition or upgrade is needed and the identity, if any, of the beneficiaries, including any determination by FERC or on appeal of a FERC determination in accordance with that process, shall be final.the
Appears in 1 contract
Sources: Transmission Control Agreement
Economically Driven Projects. The determination that a transmission addition or upgrade is needed to promote economic efficiency shall be made in any of the following ways:
3.2.1.1.1 If the Participating TO or any party questions the economic need for the project (except where the Project Sponsor commits to pay the full cost of construction) the proposal will be submitted to the ISO ADR Procedures for resolution.
3.2.1.1.2 Where a Project Sponsor other than the Participating TO commits to pay the full cost of construction of a transmission addition or upgrade and its operation, and demonstrates to the ISO financial capability to pay those costs, such commitment and demonstration shall be sufficient to demonstrate need. To ensure that the Project Sponsor is financially able to pay the costs of the project to be constructed by the Participating TO, the Participating TO may require (1) a demonstration of creditworthiness (e.g. an appropriate credit rating), or (2) sufficient security in the form of an unconditional and irrevocable letter of credit or other similar security sufficient to meet its responsibilities and obligations for the full costs of the transmission addition or upgrade.
3.2.1.1.3 Where a Project Sponsor asserts that a transmission addition or upgrade is economically beneficial, but that Project Sponsor is unwilling to commit to pay the full cost of the addition or upgrade; where (1) the proposed transmission expansion or upgrade was submitted to the Participating TO but was not included in the transmission expansion plan of that Participating TO in accordance with Section 3.2.2 or (2) the operation date of the planned expansion is not acceptable to the ISO or the Project Sponsor or (3) the Participating TO unreasonably delays implementing or subsequently decides not to proceed with the project, the Project Sponsor may submit its proposal to the ISO ADR Procedure for determination of need. A determination of need shall be made as follows:Section
3.2.1.1.3.1 The Project Sponsor shall include in its proposal a showing: (1) that the economic benefits of the proposed transmission addition or upgrade are expected to exceed its costs (giving consideration to any reasonable alternatives to the construction of transmission additions or upgrades), and (2) a proposed pricing methodology for the transmission upgrades that, to the extent practicable, assigns the costs of the planned upgrades to the beneficiaries in proportion to their net benefits.
3.2.1.1.3.2 If neither any Market Participant nor the ISO disputes the Project Sponsor’s showing, then the proposal is determined to be needed.
3.2.1.1.3.3 If any Market Participant or the ISO disputes the Project Sponsor’s showing, then if the proposed transmission addition or upgrade is determined to be needed, the disputing Market Participant, the ISO, or the Project Sponsor may submit to resolution through the ISO ADR Procedure the issues of (1) whether the transmission addition or upgrade is needed on the ground that its economic benefits exceed its costs, (2) whether the beneficiaries of the transmission addition or upgrade can reasonably be identified, and (3) if so, the identity of those beneficiaries and their respective net benefits. If a Market Participant fails to raise through the ISO ADR Procedure a dispute as to whether a proposed transmission addition or upgrade is needed, or as to the identity, if any, of the beneficiary, then the Market Participant shall be deemed to have waived its right to raise such dispute at a later date. The determination under the ISO ADR Procedure as to whether the transmission addition or upgrade is needed and the identity, if any, of the beneficiaries, including any determination by FERC or on appeal of a FERC determination in accordance with that process, shall be final.and
Appears in 1 contract
Sources: Transmission Control Agreement
Economically Driven Projects. The determination that a transmission addition or upgrade is needed to promote economic efficiency shall be made in any of the following ways:
3.2.1.1.1 If the Participating TO or any party questions the economic need for the project (except where the Project Sponsor commits to pay the full cost of construction) the proposal will be submitted to the ISO ADR Procedures for resolution.
3.2.1.1.2 Where a Project Sponsor other than the Participating TO commits to pay the full cost of construction of a transmission addition or upgrade and its operation, and demonstrates to the ISO financial capability to pay those costs, such commitment and demonstration shall be sufficient to demonstrate need. To ensure that the Project Sponsor is financially able to pay the costs of the project to be constructed by the Participating TO, the Participating TO may require (1) a demonstration of creditworthiness (e.g. an appropriate credit rating), or (2) sufficient security in the form of an unconditional and irrevocable letter of credit or other similar security sufficient to meet its responsibilities and obligations for the full costs of the transmission addition or upgrade.
3.2.1.1.3 Where a Project Sponsor asserts that a transmission addition or upgrade is economically beneficial, but that Project Sponsor is unwilling to commit to pay the full cost of the addition or upgrade; where (1) the proposed transmission expansion or upgrade was submitted to the Participating TO but was not included in the transmission expansion plan of that Participating TO in accordance with Section 3.2.2 or (2) the operation date of the planned expansion is not acceptable to the ISO or the Project Sponsor or (3) the Participating TO unreasonably delays implementing or subsequently decides not to proceed with the project, the Project Sponsor may submit its proposal to the ISO ADR Procedure for determination of need. A determination of need shall be made as follows:subsequently
3.2.1.1.3.1 The Project Sponsor shall include in its proposal a showing: (1) that the economic benefits of the proposed transmission addition or upgrade are expected to exceed its costs (giving consideration to any reasonable alternatives to the construction of transmission additions or upgrades), and (2) a proposed pricing methodology for the transmission upgrades that, to the extent practicable, assigns the costs of the planned upgrades to the beneficiaries in proportion to their net benefits.
3.2.1.1.3.2 If neither any Market Participant nor the ISO disputes the Project Sponsor’s showing, then the proposal is determined to be needed.
3.2.1.1.3.3 If any Market Participant or the ISO disputes the Project Sponsor’s showing, then if the proposed transmission addition or upgrade is determined to be needed, the disputing Market Participant, the ISO, or the Project Sponsor may submit to resolution through the ISO ADR Procedure the issues of (1) whether the transmission addition or upgrade is needed on the ground that its economic benefits exceed its costs, (2) whether the beneficiaries of the transmission addition or upgrade can reasonably be identified, and (3) if so, the identity of those beneficiaries and their respective net benefits. If a Market Participant fails to raise through the ISO ADR Procedure a dispute as to whether a proposed transmission addition or upgrade is needed, or as to the identity, if any, of the beneficiary, then the Market Participant shall be deemed to have waived its right to raise such dispute at a later date. The determination under the ISO ADR Procedure as to whether the transmission addition or upgrade is needed and the identity, if any, of the beneficiaries, including any determination by FERC or on appeal of a FERC determination in accordance with that process, shall be final.any
Appears in 1 contract
Sources: Transmission Control Agreement
Economically Driven Projects. The determination that a transmission addition or upgrade is needed to promote economic efficiency shall be made in any of the following ways:
3.2.1.1.1 If the Participating TO or any party questions the economic need for the project (except where the Project Sponsor commits to pay the full cost of construction) the proposal will be submitted to the ISO ADR Procedures for resolution.
3.2.1.1.2 Where a Project Sponsor other than the Participating TO commits to pay the full cost of construction of a transmission addition or upgrade and its operation, and demonstrates to the ISO financial capability to pay those costs, such commitment and demonstration shall be sufficient to demonstrate need. To ensure that the Project Sponsor is financially able to pay the costs of the project to be constructed by the Participating TO, the Participating TO may require (1) a demonstration of creditworthiness (e.g. an appropriate credit rating), or (2) sufficient security in the form of an unconditional and irrevocable letter of credit or other similar security sufficient to meet its responsibilities and obligations for the full costs of the transmission addition or upgrade.
3.2.1.1.3 Where a Project Sponsor asserts that a transmission addition or upgrade is economically beneficial, but that Project Sponsor is unwilling to commit to pay the full cost of the addition or upgrade; where (1) the proposed transmission expansion or upgrade was submitted to the Participating TO but was not included in the transmission expansion plan of that Participating TO in accordance with Section 3.2.2 or (2) the operation date of the planned expansion is not acceptable to the ISO or the Project Sponsor or (3) the Participating TO unreasonably delays implementing or subsequently decides not to proceed with the project, the Project Sponsor may submit its proposal to the ISO ADR Procedure for determination of need. A determination of need shall be made as follows:Section
3.2.1.1.3.1 The Project Sponsor shall include in its proposal a showing: (1) that the economic benefits of the proposed transmission addition or upgrade are expected to exceed its costs (giving consideration to any reasonable alternatives to the construction of transmission additions or upgrades), and (2) a proposed pricing methodology for the transmission upgrades that, to the extent practicable, assigns the costs of the planned upgrades to the beneficiaries in proportion to their net benefits.
3.2.1.1.3.2 If neither any Market Participant nor the ISO disputes the Project Sponsor’s showing, then the proposal is determined to be needed.
3.2.1.1.3.3 If any Market Participant or the ISO disputes the Project Sponsor’s showing, then if the proposed transmission addition or upgrade is determined to be needed, the disputing Market Participant, the ISO, or the Project Sponsor may submit to resolution through the ISO ADR Procedure the issues of (1) whether the transmission addition or upgrade is needed on the ground that its economic benefits exceed its costs, (2) whether the beneficiaries of the transmission addition or upgrade can reasonably be identified, and (3) if so, the identity of those beneficiaries and their respective net benefits. If a Market Participant fails to raise through the ISO ADR Procedure a dispute as to whether a proposed transmission addition or upgrade is needed, or as to the identity, if any, of the beneficiary, then the Market Participant shall be deemed to have waived its right to raise such dispute at a later date. The determination under the ISO ADR Procedure as to whether the transmission addition or upgrade is needed and the identity, if any, of the beneficiaries, including any determination by FERC or on appeal of a FERC determination in accordance with that process, shall be final.,
Appears in 1 contract
Sources: Transmission Control Agreement