Effect of Force Majeure on Capacity Payments Sample Clauses

The 'Effect of Force Majeure on Capacity Payments' clause defines how capacity payments are handled when a force majeure event occurs. Typically, this clause outlines whether the party affected by force majeure will continue to receive or be required to make capacity payments during the period when their performance is hindered by circumstances beyond their control, such as natural disasters or government actions. For example, if a power plant cannot generate electricity due to a flood, the clause will specify if the plant owner still receives payment for maintaining capacity. The core function of this clause is to allocate financial risk and clarify payment obligations during unforeseen disruptions, ensuring both parties understand their rights and responsibilities in such situations.
Effect of Force Majeure on Capacity Payments. For purposes of, and pursuant to, the monthly Capacity Payment calculation specified in Appendix B, a Participating Facility’s Contract Capacity shall be considered to be unavailable during all hours where AER is unable to provide or deliver such Contract Capacity due to an event of Force Majeure (i.e., no Capacity Payment is required to be made), provided, that such event is not caused by, and does not result from, CL&P’s failure to perform in accordance with the provisions of this Agreement.
Effect of Force Majeure on Capacity Payments. For purposes of, and pursuant to, the monthly Capacity Payment calculation specified in Appendix B, a Participating Facility’s Contract Capacity shall be considered to be unavailable during all hours where Comverge is unable to provide or deliver such Contract Capacity due to an event of Force Majeure, provided, that such event is not caused by, and does not result from, PNM’s failure to perform in accordance with the provisions of this Agreement.

Related to Effect of Force Majeure on Capacity Payments

  • Effect of Force Majeure Event If either party to this contract cannot meet an obligation under this contract because of an event outside the control of that party (‘a force majeure event’): (a) the obligation, other than an obligation to pay money, is suspended to the extent it is affected by the force majeure event for as long as the force majeure event continues; and (b) the affected party must use its best endeavours to give the other party prompt notice of that fact including full particulars of the event, an estimate of its likely duration, the extent to which the affected party’s obligations are affected and the steps being taken to remove, overcome or minimise those effects.

  • Effect of Force Majeure If either Party is rendered wholly or partially unable to perform its obligations under this Agreement because of a Force Majeure Act, that Party shall be excused from whatever performance is affected by the Force Majeure Act to the extent so affected, provided that: a) Within five (5) Business Days after the occurrence of the inability to perform due to a Force Majeure Act, the Affected Party provides a written notice to the other Party of the particulars of the occurrence, including an estimation of its expected duration and probable impact on the performance of its obligations hereunder, and continues to furnish periodic reports with respect thereto, every seven (7) days, during the period of Force Majeure, b) The Affected Party shall use all reasonable efforts to continue to perform its obligations hereunder and to correct or cure as soon as possible the Force Majeure Act, c) The suspension of performance shall be of no greater scope and no longer duration than is reasonably necessitated by the Force Majeure Act, d) The Affected Party shall provide the other Party with prompt notice of the cessation of the Force Majeure Act giving rise to the excuse from performance and shall thereupon resume normal performance of obligations under this Agreement with utmost promptitude, e) The non-performance of any obligation of either Party that was required to be performed prior to the occurrence of a Force Majeure Act shall not be excused as a result of such subsequent Force Majeure Act, f) The occurrence of a Force Majeure Act shall not relieve either Party from its obligations to make any payment hereunder for performance rendered prior to the occurrence of Force Majeure Act or for partial performance hereunder during period of subsistence Force Majeure Act; and g) The Force Majeure Act, shall not relieve either Party from its obligation to comply with Applicable Laws. The Affected Party shall exercise all reasonable efforts to mitigate or limit damages to the other Party.

  • Force Majeure, Notice of Delay, and No Damages for Delay The Contractor will not be responsible for delay resulting from its failure to perform if neither the fault nor the negligence of the Contractor or its employees, subcontractors, or agents contributed to the delay and the delay is due directly to acts of God, wars, acts of public enemies, strikes, fires, floods, or other similar cause wholly beyond the Contractor’s control, or for any of the foregoing that affect suppliers if no alternate source of supply is available to the Contractor. In case of any delay the Contractor believes is excusable, the Contractor shall notify the Department in writing of the delay or potential delay and describe the cause of the delay either (i) within ten (10) calendar days after the cause that creates or will create the delay first arose, if the Contractor could reasonably foresee that a delay could occur as a result; or (ii) if a delay is not reasonably foreseeable, within five (5) calendar days after the date the Contractor first had reason to believe that a delay could result. THE FOREGOING WILL CONSTITUTE THE CONTRACTOR’S SOLE REMEDY OR EXCUSE WITH RESPECT TO ANY DELAY except if such delay is caused by the fraud, bad faith, or active interference of the Department. Providing notice in strict accordance with this paragraph is a condition precedent to such remedy, and a rebuttable presumption of prejudice will exist based on Contractor’s untimely notice. The Contractor shall not assert any claim for damages related to such delay. The Contractor will not be entitled to an increase in the Term Contract price or payment of any kind from the Department for direct, indirect, consequential, impact, or other costs, expenses, or damages, including costs of acceleration or inefficiency, arising because of delay, disruption, interference, or hindrance from any cause whatsoever. If performance is suspended or delayed, in whole or in part, due to any of the causes described in this subsection, the Department may unilaterally (and with no recourse on the part of the Contractor) identify and use an alternate source to complete any work under the Term Contract as the Department deems necessary, in its sole discretion. After the causes have ceased to exist, the Contractor shall perform at no increased cost, unless the Department determines, in its sole discretion, that the delay will significantly impair the value of the Contract to the Department or State, in which case the Department may (i) accept allocated performance or deliveries from the Contractor, provided that the Contractor grants preferential treatment to the Department with respect to Products subjected to allocation; or (ii) terminate the Term Contract in whole or in part.

  • Entitlement to Force Majeure relief An Affected Party is entitled to Force Majeure relief if and to the extent that: (a) performance of the Relevant Obligation has been prevented or materially impeded by reason of a Force Majeure Event; (b) it has taken all reasonable steps, taking account of all relevant circumstances (including as to whether the event in question could reasonably have been anticipated): (i) to avoid the occurrence of the Force Majeure Event; and (ii) to minimise, and where practicable avoid, the effects of the Force Majeure Event on its ability to perform the Relevant Obligation; and (c) except in the case of clause 17.1(f), none of the Affected Party, its officers, employees or agents caused the Force Majeure Event.

  • Notification of Force Majeure Event 11.5.1 The Affected Party shall give notice to the other Party of any event of Force Majeure as soon as reasonably practicable, but not later than seven (7) days after the date on which such Party knew or should reasonably have known of the commencement of the event of Force Majeure. If an event of Force Majeure results in a breakdown of communications rendering it unreasonable to give notice within the applicable time limit specified herein, then the Party claiming Force Majeure shall give such notice as soon as reasonably practicable after reinstatement of communications, but not later than one (1) day after such reinstatement. Provided that, such notice shall be a pre-condition to the Affected Party’s entitlement to claim relief under this Agreement. Such notice shall include full particulars of the event of Force Majeure, its effects on the Party claiming relief and the remedial measures proposed. The Affected Party shall give the other Party regular reports on the progress of those remedial measures and such other information as the other Party may reasonably request about the Force Majeure. 11.5.2 The Affected Party shall give notice to the other Party of (i) the cessation of the relevant event of Force Majeure; and (ii) the cessation of the effects of such event of Force Majeure on the performance of its rights or obligations/ roles under this Agreement, as soon as practicable after becoming aware of each of these cessations.